turnaround_id,refinery_id,unit_id,shutdown_type,planned_start_date,planned_duration_days,actual_duration_days,schedule_slippage_pct,scope_complexity_score,feed_rate_loss_bpd,regulatory_driver_flag,weather_disruption_flag TA-00000001,REF-0003,Delayed Coker,Planned Turnaround,2025-11-17,29,32,9.76,0.54,16062,0,0 TA-00000002,REF-0014,Hydrotreating,Emergency Shutdown,2019-06-20,8,10,14.97,0.592,30368,1,0 TA-00000003,REF-0015,Hydrocracker,Pitstop,2019-02-08,8,10,16.7,0.772,103903,0,0 TA-00000004,REF-0001,Alkylation,Regulatory Outage,2027-12-20,23,25,8.49,0.966,32497,1,1 TA-00000005,REF-0012,Delayed Coker,Pitstop,2025-01-07,9,11,13.66,0.763,108500,0,0 TA-00000006,REF-0007,Reformer,Major Turnaround,2022-08-20,43,49,12.39,0.518,43020,0,0 TA-00000007,REF-0006,Reformer,Planned Turnaround,2027-03-06,14,16,9.87,0.832,18573,0,0 TA-00000008,REF-0009,Utilities,Planned Turnaround,2025-07-21,28,32,13.4,0.941,75959,1,0 TA-00000009,REF-0007,Cooling Water,Pitstop,2019-08-02,11,13,12.76,0.687,37113,0,0 TA-00000010,REF-0007,CDU,Planned Turnaround,2024-07-26,38,44,15.26,0.66,56444,0,0 TA-00000011,REF-0005,Cooling Water,Planned Turnaround,2020-09-13,25,29,14.5,0.609,15685,0,0 TA-00000012,REF-0011,Tank Farm,Pitstop,2021-01-13,8,9,10.24,0.45,64653,0,0 TA-00000013,REF-0006,Reformer,Planned Turnaround,2026-06-30,18,20,10.6,0.566,74520,0,0 TA-00000014,REF-0001,Cooling Water,Pitstop,2019-02-24,15,16,2.93,0.705,38007,0,0 TA-00000015,REF-0008,FCCU,Pitstop,2026-09-14,11,12,7.15,0.739,34087,1,0 TA-00000016,REF-0010,Utilities,Planned Turnaround,2025-06-16,19,22,13.02,0.758,20604,0,0 TA-00000017,REF-0008,FCCU,Planned Turnaround,2026-11-11,24,27,10.97,0.573,34063,0,0 TA-00000018,REF-0007,Tank Farm,Major Turnaround,2025-09-23,32,39,20.22,0.679,91717,0,0 TA-00000019,REF-0014,Hydrogen Plant,Planned Turnaround,2020-10-12,35,39,11.18,0.689,25326,0,0 TA-00000020,REF-0003,Utilities,Planned Turnaround,2023-04-28,27,31,13.65,0.536,118369,0,0 TA-00000021,REF-0007,FCCU,Planned Turnaround,2027-06-19,31,38,19.97,0.477,122490,0,0 TA-00000022,REF-0011,Delayed Coker,Regulatory Outage,2021-01-12,20,24,16.03,0.337,110807,1,1 TA-00000023,REF-0015,Flare System,Planned Turnaround,2023-07-15,27,30,8.99,0.773,113891,0,0 TA-00000024,REF-0003,Sulfur Recovery,Planned Turnaround,2022-11-04,10,12,16.13,0.775,144765,0,0 TA-00000025,REF-0009,VDU,Planned Turnaround,2020-11-01,35,39,11.04,0.687,51056,0,0 TA-00000026,REF-0004,Sulfur Recovery,Pitstop,2023-12-09,15,17,11.13,0.679,39378,0,0 TA-00000027,REF-0011,Flare System,Planned Turnaround,2021-05-19,40,43,6.9,0.296,123032,1,0 TA-00000028,REF-0014,CDU,Emergency Shutdown,2020-04-13,4,5,9.51,0.673,46306,0,0 TA-00000029,REF-0001,Alkylation,Planned Turnaround,2027-05-29,20,24,15.7,0.48,137835,0,0 TA-00000030,REF-0015,Hydrotreating,Planned Turnaround,2025-07-06,23,27,16.45,0.713,72409,1,0 TA-00000031,REF-0014,Reformer,Planned Turnaround,2028-08-12,32,38,15.87,0.483,16191,0,0 TA-00000032,REF-0009,Delayed Coker,Planned Turnaround,2027-11-29,25,28,10.89,0.507,35367,0,0 TA-00000033,REF-0011,Hydrocracker,Major Turnaround,2020-12-09,26,30,15.13,0.548,58518,0,1 TA-00000034,REF-0012,Cooling Water,Planned Turnaround,2021-12-20,29,32,8.61,0.744,130109,0,0 TA-00000035,REF-0007,Hydrotreating,Planned Turnaround,2023-08-21,16,17,5.57,0.883,57059,0,0 TA-00000036,REF-0011,Sulfur Recovery,Pitstop,2023-12-08,6,7,16.38,0.409,57186,0,0 TA-00000037,REF-0001,Hydrocracker,Major Turnaround,2021-03-05,37,40,7.35,0.62,131187,0,0 TA-00000038,REF-0002,Hydrogen Plant,Planned Turnaround,2024-06-04,21,24,10.3,0.617,33083,0,0 TA-00000039,REF-0011,Flare System,Planned Turnaround,2024-01-05,24,28,16.01,0.629,105866,0,0 TA-00000040,REF-0003,Hydrocracker,Planned Turnaround,2021-06-30,22,26,14.94,0.511,59910,0,0 TA-00000041,REF-0012,CDU,Regulatory Outage,2019-11-26,19,21,8.7,0.533,99464,1,0 TA-00000042,REF-0004,Tank Farm,Planned Turnaround,2020-12-26,31,36,15.32,0.51,20124,0,0 TA-00000043,REF-0001,FCCU,Planned Turnaround,2023-11-13,23,26,10.46,0.881,19556,1,0 TA-00000044,REF-0015,Tank Farm,Planned Turnaround,2021-10-06,18,21,16.51,0.536,151462,0,0 TA-00000045,REF-0015,Utilities,Regulatory Outage,2020-03-28,14,17,15.84,0.68,40138,1,0 TA-00000046,REF-0011,Reformer,Major Turnaround,2019-07-23,55,66,19.15,0.833,25431,0,0 TA-00000047,REF-0009,FCCU,Planned Turnaround,2028-10-19,30,33,9.28,0.913,58539,0,0 TA-00000048,REF-0003,Sulfur Recovery,Planned Turnaround,2023-01-30,32,35,7.5,0.435,100243,0,1 TA-00000049,REF-0007,Utilities,Planned Turnaround,2023-07-20,19,21,6.48,0.512,136789,0,0 TA-00000050,REF-0012,VDU,Planned Turnaround,2023-03-08,24,28,16.23,0.516,48426,1,0 TA-00000051,REF-0015,Hydrotreating,Emergency Shutdown,2021-01-18,4,5,4.93,0.539,41673,0,0 TA-00000052,REF-0015,Reformer,Planned Turnaround,2026-02-27,17,19,9.9,0.681,131190,1,0 TA-00000053,REF-0005,Flare System,Planned Turnaround,2019-01-20,23,26,8.72,0.951,77747,0,0 TA-00000054,REF-0006,Cooling Water,Pitstop,2020-02-20,11,12,8.97,0.401,94344,0,0 TA-00000055,REF-0005,Hydrocracker,Regulatory Outage,2022-04-20,19,22,13.36,0.693,94062,1,0 TA-00000056,REF-0006,Sulfur Recovery,Planned Turnaround,2025-07-21,33,40,18.94,0.636,86416,0,0 TA-00000057,REF-0007,Delayed Coker,Pitstop,2028-04-06,9,11,13.82,0.738,64802,0,0 TA-00000058,REF-0003,Hydrotreating,Emergency Shutdown,2022-04-15,3,4,7.99,0.836,127425,0,0 TA-00000059,REF-0007,Alkylation,Planned Turnaround,2021-06-05,31,33,5.34,0.625,101352,0,0 TA-00000060,REF-0007,CDU,Planned Turnaround,2019-06-07,25,28,11.17,0.655,118843,0,0 TA-00000061,REF-0009,Tank Farm,Planned Turnaround,2027-01-12,26,28,7.4,0.457,54241,0,0 TA-00000062,REF-0005,Hydrogen Plant,Planned Turnaround,2026-05-02,23,28,19.34,0.801,36961,0,0 TA-00000063,REF-0009,VDU,Planned Turnaround,2027-11-12,35,37,4.58,0.46,34688,0,0 TA-00000064,REF-0006,Hydrotreating,Pitstop,2024-12-21,11,13,9.45,0.785,20639,0,0 TA-00000065,REF-0007,Hydrotreating,Major Turnaround,2023-01-07,41,46,10.43,0.673,120104,1,0 TA-00000066,REF-0008,VDU,Planned Turnaround,2024-06-16,15,17,11.44,0.838,53928,0,0 TA-00000067,REF-0009,Reformer,Planned Turnaround,2026-01-27,27,31,13.22,0.697,62001,0,0 TA-00000068,REF-0015,FCCU,Major Turnaround,2027-06-19,28,31,8.48,0.694,161389,0,0 TA-00000069,REF-0002,Hydrotreating,Planned Turnaround,2022-04-07,35,42,18.1,0.509,42892,0,0 TA-00000070,REF-0012,Hydrocracker,Pitstop,2019-12-13,12,15,17.38,0.601,112816,0,0 TA-00000071,REF-0012,Delayed Coker,Planned Turnaround,2024-02-04,30,35,14.22,0.781,127765,1,0 TA-00000072,REF-0009,CDU,Major Turnaround,2025-03-10,31,37,17.46,0.523,68413,0,0 TA-00000073,REF-0015,Flare System,Pitstop,2022-07-19,7,9,14.88,0.77,117903,0,0 TA-00000074,REF-0013,Cooling Water,Planned Turnaround,2022-08-24,32,38,16.86,0.214,98874,0,0 TA-00000075,REF-0008,Hydrotreating,Planned Turnaround,2026-03-19,17,19,11.32,0.902,28596,0,0 TA-00000076,REF-0008,Delayed Coker,Regulatory Outage,2028-07-03,14,15,6.74,0.915,60493,1,0 TA-00000077,REF-0008,VDU,Major Turnaround,2027-01-04,28,32,13.42,0.581,48209,1,0 TA-00000078,REF-0013,Alkylation,Major Turnaround,2019-08-21,38,42,9.06,0.685,36712,0,0 TA-00000079,REF-0006,Flare System,Planned Turnaround,2019-04-10,27,33,19.28,0.358,60181,0,0 TA-00000080,REF-0005,Hydrotreating,Planned Turnaround,2026-11-26,37,42,11.48,0.847,40920,0,0 TA-00000081,REF-0006,Delayed Coker,Pitstop,2022-01-07,11,13,15.52,0.488,66712,0,0 TA-00000082,REF-0006,Cooling Water,Pitstop,2019-04-18,10,12,14.83,0.589,12304,0,0 TA-00000083,REF-0010,Reformer,Pitstop,2019-01-15,9,11,11.46,0.874,21930,0,0 TA-00000084,REF-0014,Utilities,Planned Turnaround,2020-12-29,30,36,16.71,0.729,44979,0,0 TA-00000085,REF-0001,Delayed Coker,Major Turnaround,2028-01-16,36,40,9.95,0.401,52880,0,0 TA-00000086,REF-0001,CDU,Major Turnaround,2024-10-29,44,49,9.14,0.566,130393,0,0 TA-00000087,REF-0009,CDU,Planned Turnaround,2023-02-04,29,33,11.47,0.447,30460,0,0 TA-00000088,REF-0009,VDU,Planned Turnaround,2025-02-12,21,24,10.28,0.669,8856,0,0 TA-00000089,REF-0004,Reformer,Emergency Shutdown,2028-02-07,6,8,17.06,0.864,52440,0,0 TA-00000090,REF-0004,CDU,Regulatory Outage,2028-08-27,19,22,13.99,0.478,14922,1,0 TA-00000091,REF-0005,CDU,Major Turnaround,2023-11-01,68,75,9.79,0.625,105812,0,0 TA-00000092,REF-0004,Hydrogen Plant,Emergency Shutdown,2019-01-04,11,13,13.77,0.52,69947,0,0 TA-00000093,REF-0015,Cooling Water,Planned Turnaround,2028-08-18,18,21,15.67,0.596,111392,1,0 TA-00000094,REF-0011,Hydrotreating,Major Turnaround,2020-03-21,37,41,10.41,0.647,69114,0,0 TA-00000095,REF-0014,Hydrotreating,Major Turnaround,2019-08-20,37,41,8.56,0.641,31457,0,0 TA-00000096,REF-0006,CDU,Pitstop,2024-01-19,13,15,13.89,0.744,19806,0,0 TA-00000097,REF-0013,FCCU,Regulatory Outage,2019-09-19,15,22,42.17,0.262,30603,1,0 TA-00000098,REF-0008,CDU,Regulatory Outage,2019-04-23,22,26,14.29,0.655,79312,1,0 TA-00000099,REF-0006,Cooling Water,Major Turnaround,2022-11-26,33,50,49.2,0.883,60287,0,0 TA-00000100,REF-0010,Tank Farm,Pitstop,2022-05-24,8,10,13.21,0.664,58943,0,0 TA-00000101,REF-0008,Flare System,Pitstop,2019-12-07,13,20,48.98,0.589,31909,0,0 TA-00000102,REF-0013,Reformer,Major Turnaround,2027-02-06,27,31,11.25,0.421,42462,0,0 TA-00000103,REF-0008,CDU,Major Turnaround,2019-04-11,40,45,11.33,0.778,48202,0,0 TA-00000104,REF-0005,VDU,Emergency Shutdown,2019-04-01,9,11,17.36,0.403,45428,0,0 TA-00000105,REF-0008,Hydrotreating,Regulatory Outage,2023-03-24,19,22,12.48,0.325,82810,1,0 TA-00000106,REF-0009,Cooling Water,Planned Turnaround,2023-02-10,19,22,12.17,0.759,37525,0,0 TA-00000107,REF-0005,Alkylation,Planned Turnaround,2028-07-03,22,25,9.09,0.678,110280,0,0 TA-00000108,REF-0010,CDU,Planned Turnaround,2022-03-15,23,27,14.62,0.697,15377,0,0 TA-00000109,REF-0008,Flare System,Major Turnaround,2022-06-21,32,36,10.32,0.712,21276,0,1 TA-00000110,REF-0015,Alkylation,Planned Turnaround,2025-11-01,20,22,5.84,0.622,104864,0,0 TA-00000111,REF-0005,Alkylation,Regulatory Outage,2023-04-12,18,21,12.51,0.707,16087,1,0 TA-00000112,REF-0003,Hydrocracker,Planned Turnaround,2026-07-27,28,32,11.38,0.765,112375,0,0 TA-00000113,REF-0014,Flare System,Planned Turnaround,2025-11-07,20,23,10.99,0.329,54373,0,1 TA-00000114,REF-0002,Cooling Water,Planned Turnaround,2028-09-03,33,38,12.75,0.622,93256,0,0 TA-00000115,REF-0004,Hydrogen Plant,Planned Turnaround,2019-02-12,16,18,11.83,0.428,49856,0,0 TA-00000116,REF-0008,Cooling Water,Major Turnaround,2020-03-31,37,41,9.67,0.957,55048,0,0 TA-00000117,REF-0006,Hydrocracker,Planned Turnaround,2027-01-03,35,39,10.05,0.55,72062,0,0 TA-00000118,REF-0003,Hydrotreating,Major Turnaround,2026-10-27,26,30,11.64,0.6,48026,0,0 TA-00000119,REF-0004,Hydrogen Plant,Planned Turnaround,2021-08-15,31,34,8.97,0.842,23020,0,0 TA-00000120,REF-0007,Sulfur Recovery,Planned Turnaround,2021-11-10,34,37,6.79,0.494,101446,0,0 TA-00000121,REF-0015,Flare System,Planned Turnaround,2019-11-02,20,22,8.41,0.705,127816,0,0 TA-00000122,REF-0001,Tank Farm,Planned Turnaround,2025-10-31,27,40,47.31,0.885,43269,0,0 TA-00000123,REF-0009,Hydrocracker,Regulatory Outage,2025-06-12,11,13,9.42,0.623,45255,1,0 TA-00000124,REF-0013,Utilities,Planned Turnaround,2025-11-30,31,35,11.09,0.769,60056,1,0 TA-00000125,REF-0003,Hydrotreating,Planned Turnaround,2023-11-29,23,27,15.79,0.567,67279,0,0 TA-00000126,REF-0005,Tank Farm,Planned Turnaround,2028-04-28,30,36,18.88,0.723,84903,0,0 TA-00000127,REF-0015,Hydrogen Plant,Planned Turnaround,2024-01-27,18,22,17.2,0.754,41565,0,0 TA-00000128,REF-0001,CDU,Planned Turnaround,2020-04-22,24,26,5.96,0.441,26809,0,0 TA-00000129,REF-0012,Hydrogen Plant,Planned Turnaround,2019-08-18,27,30,8.46,0.642,92742,0,1 TA-00000130,REF-0013,Hydrogen Plant,Planned Turnaround,2028-01-27,25,27,5.3,0.499,39405,0,0 TA-00000131,REF-0007,Hydrotreating,Regulatory Outage,2023-01-15,10,11,8.46,0.949,94841,1,0 TA-00000132,REF-0010,FCCU,Major Turnaround,2020-09-09,55,63,12.91,0.714,83565,1,0 TA-00000133,REF-0013,CDU,Regulatory Outage,2021-01-15,16,18,10.31,0.72,12544,1,0 TA-00000134,REF-0011,Sulfur Recovery,Pitstop,2026-02-27,9,10,9.55,0.524,117098,0,0 TA-00000135,REF-0013,Sulfur Recovery,Major Turnaround,2023-02-03,54,65,20.3,0.718,63172,0,0 TA-00000136,REF-0014,Flare System,Major Turnaround,2025-02-01,28,32,13.47,0.847,16980,1,0 TA-00000137,REF-0012,Sulfur Recovery,Planned Turnaround,2023-11-11,20,23,11.81,0.575,154663,0,0 TA-00000138,REF-0005,Sulfur Recovery,Planned Turnaround,2026-05-22,21,23,7.62,0.589,104469,0,0 TA-00000139,REF-0014,Sulfur Recovery,Planned Turnaround,2023-01-27,33,36,6.92,0.799,19841,0,0 TA-00000140,REF-0005,Tank Farm,Planned Turnaround,2024-03-25,21,24,13.53,0.454,105978,0,0 TA-00000141,REF-0005,Sulfur Recovery,Regulatory Outage,2019-07-17,19,23,18.44,0.804,35818,1,0 TA-00000142,REF-0002,Delayed Coker,Planned Turnaround,2026-03-14,23,27,13.39,0.533,122320,0,0 TA-00000143,REF-0001,Reformer,Major Turnaround,2019-01-01,42,60,41.4,0.703,117854,0,0 TA-00000144,REF-0013,Hydrotreating,Planned Turnaround,2024-06-16,25,29,12.48,0.747,105247,0,0 TA-00000145,REF-0002,Reformer,Planned Turnaround,2028-02-07,18,22,17.97,0.944,22927,0,0 TA-00000146,REF-0005,VDU,Regulatory Outage,2020-03-17,20,23,11.94,0.653,44163,1,0 TA-00000147,REF-0001,Flare System,Planned Turnaround,2019-09-20,33,38,14.34,0.87,26284,0,0 TA-00000148,REF-0009,Sulfur Recovery,Planned Turnaround,2025-07-01,34,38,9.36,0.396,10874,0,0 TA-00000149,REF-0009,Reformer,Planned Turnaround,2025-08-24,30,36,19.38,0.98,13329,0,0 TA-00000150,REF-0011,VDU,Planned Turnaround,2022-10-08,19,21,7.87,0.699,49705,0,0 TA-00000151,REF-0003,Tank Farm,Planned Turnaround,2025-10-04,24,26,8.04,0.648,57617,0,0 TA-00000152,REF-0002,Reformer,Planned Turnaround,2025-12-14,22,26,18.16,0.841,62379,0,0 TA-00000153,REF-0003,Utilities,Planned Turnaround,2026-08-05,11,13,14.73,0.769,134082,0,0 TA-00000154,REF-0013,VDU,Regulatory Outage,2026-03-13,17,19,8.02,0.543,29185,1,0 TA-00000155,REF-0003,FCCU,Planned Turnaround,2020-05-30,21,24,10.72,0.854,55916,0,0 TA-00000156,REF-0001,Tank Farm,Pitstop,2020-05-02,12,15,17.4,0.174,97770,0,0 TA-00000157,REF-0005,VDU,Major Turnaround,2019-02-03,37,41,8.28,0.418,47537,1,0 TA-00000158,REF-0009,Hydrocracker,Emergency Shutdown,2021-04-09,3,4,13.19,0.601,77525,0,0 TA-00000159,REF-0004,Delayed Coker,Planned Turnaround,2027-11-09,22,25,12.75,0.619,37782,0,0 TA-00000160,REF-0014,Sulfur Recovery,Emergency Shutdown,2024-05-07,7,8,12.52,0.704,7757,0,0 TA-00000161,REF-0006,Hydrocracker,Pitstop,2022-04-17,4,5,16.87,0.834,42804,0,0 TA-00000162,REF-0003,Utilities,Emergency Shutdown,2021-05-31,3,4,5.55,0.607,100689,0,0 TA-00000163,REF-0006,Flare System,Pitstop,2021-10-10,8,9,4.42,0.735,44251,0,0 TA-00000164,REF-0007,FCCU,Pitstop,2025-05-06,8,10,15.8,0.352,104115,0,0 TA-00000165,REF-0012,Reformer,Major Turnaround,2028-11-12,58,64,9.08,0.625,62185,0,0 TA-00000166,REF-0010,CDU,Pitstop,2023-03-16,7,9,15.5,0.323,45619,0,0 TA-00000167,REF-0002,Sulfur Recovery,Planned Turnaround,2022-10-15,23,25,7.67,0.431,86496,0,0 TA-00000168,REF-0011,VDU,Planned Turnaround,2028-06-25,27,28,2.17,0.492,99117,0,0 TA-00000169,REF-0015,FCCU,Planned Turnaround,2027-11-09,26,30,13.82,0.7,65026,0,0 TA-00000170,REF-0001,Flare System,Planned Turnaround,2024-12-30,27,31,11.64,0.378,94318,0,0 TA-00000171,REF-0001,Utilities,Pitstop,2023-10-15,12,14,9.35,0.765,48987,0,0 TA-00000172,REF-0007,Sulfur Recovery,Regulatory Outage,2026-08-20,17,19,11.48,0.864,102175,1,0 TA-00000173,REF-0012,Reformer,Major Turnaround,2021-07-22,44,48,7.31,0.908,39709,0,0 TA-00000174,REF-0008,Alkylation,Pitstop,2024-12-23,10,12,14.79,0.691,20277,0,0 TA-00000175,REF-0013,Hydrotreating,Major Turnaround,2020-03-16,55,63,13.58,0.516,92378,0,0 TA-00000176,REF-0014,CDU,Planned Turnaround,2026-03-16,25,28,9.48,0.475,34697,0,0 TA-00000177,REF-0015,Alkylation,Planned Turnaround,2027-12-27,24,28,14.21,0.541,32704,0,0 TA-00000178,REF-0003,Delayed Coker,Emergency Shutdown,2028-08-17,6,7,5.03,0.781,90137,0,0 TA-00000179,REF-0015,Hydrocracker,Regulatory Outage,2026-08-07,11,12,5.04,0.695,56133,1,1 TA-00000180,REF-0006,Tank Farm,Planned Turnaround,2024-08-01,29,33,10.66,0.543,55649,0,1 TA-00000181,REF-0004,Sulfur Recovery,Major Turnaround,2025-05-18,45,51,13.1,0.806,11323,1,0 TA-00000182,REF-0005,CDU,Pitstop,2023-01-21,13,15,10.8,0.557,83387,0,0 TA-00000183,REF-0015,Utilities,Emergency Shutdown,2024-01-20,4,5,9.13,0.635,74248,0,0 TA-00000184,REF-0003,Utilities,Major Turnaround,2025-12-09,31,37,17.26,0.621,32550,0,0 TA-00000185,REF-0001,Hydrocracker,Pitstop,2019-04-05,14,16,9.16,0.542,70643,0,0 TA-00000186,REF-0003,Cooling Water,Major Turnaround,2019-10-06,37,42,13.43,0.544,16633,0,0 TA-00000187,REF-0010,Tank Farm,Planned Turnaround,2024-06-01,23,26,10.64,0.57,18921,0,0 TA-00000188,REF-0011,Flare System,Pitstop,2028-04-14,10,12,13.19,0.98,93520,0,0 TA-00000189,REF-0002,Sulfur Recovery,Planned Turnaround,2026-01-18,40,44,8.95,0.66,106279,0,0 TA-00000190,REF-0002,Utilities,Planned Turnaround,2020-02-14,30,34,11.41,0.827,40102,0,0 TA-00000191,REF-0003,FCCU,Major Turnaround,2020-02-25,37,45,20.58,0.417,157581,1,0 TA-00000192,REF-0012,Hydrotreating,Emergency Shutdown,2028-09-03,4,5,11.87,0.557,103599,0,0 TA-00000193,REF-0015,CDU,Pitstop,2023-02-05,12,14,12.55,0.433,40581,0,0 TA-00000194,REF-0009,FCCU,Pitstop,2026-12-13,8,9,9.33,0.767,36250,1,0 TA-00000195,REF-0009,Cooling Water,Planned Turnaround,2025-07-18,23,25,6.79,0.694,48597,0,0 TA-00000196,REF-0012,Alkylation,Planned Turnaround,2028-03-24,37,42,13.36,0.614,68991,0,0 TA-00000197,REF-0002,Tank Farm,Planned Turnaround,2022-12-09,29,32,9.64,0.806,113600,0,0 TA-00000198,REF-0006,Hydrotreating,Major Turnaround,2028-06-22,75,85,12.43,0.899,85719,0,0 TA-00000199,REF-0001,Sulfur Recovery,Emergency Shutdown,2025-06-17,8,9,8.27,0.37,161567,0,0 TA-00000200,REF-0008,FCCU,Planned Turnaround,2021-05-31,33,36,7.74,0.628,47659,0,0 TA-00000201,REF-0012,Tank Farm,Pitstop,2027-12-11,12,14,14.63,0.98,33130,0,0 TA-00000202,REF-0006,FCCU,Regulatory Outage,2022-08-17,15,18,15.03,0.581,70221,1,0 TA-00000203,REF-0007,Sulfur Recovery,Planned Turnaround,2024-03-01,34,45,32.08,0.686,88138,0,1 TA-00000204,REF-0009,Tank Farm,Planned Turnaround,2026-07-11,27,31,14.63,0.561,50955,0,0 TA-00000205,REF-0015,FCCU,Planned Turnaround,2023-04-20,21,25,15.12,0.463,36568,0,0 TA-00000206,REF-0007,CDU,Major Turnaround,2027-02-28,32,35,7.37,0.756,135905,0,0 TA-00000207,REF-0012,Alkylation,Emergency Shutdown,2020-08-07,6,7,8.46,0.472,147165,1,0 TA-00000208,REF-0001,Hydrogen Plant,Planned Turnaround,2022-01-30,24,26,7.78,0.628,142280,0,0 TA-00000209,REF-0014,Flare System,Planned Turnaround,2024-01-28,21,25,16.64,0.549,20600,0,0 TA-00000210,REF-0007,FCCU,Planned Turnaround,2019-06-05,21,23,8.04,0.739,20439,0,0 TA-00000211,REF-0002,Utilities,Planned Turnaround,2022-12-07,24,27,9.81,0.518,114954,1,0 TA-00000212,REF-0013,Cooling Water,Planned Turnaround,2025-02-05,24,26,6.25,0.442,75287,0,0 TA-00000213,REF-0003,Alkylation,Planned Turnaround,2025-11-19,24,28,13.6,0.936,49199,1,0 TA-00000214,REF-0013,Delayed Coker,Planned Turnaround,2028-12-01,27,29,7.38,0.525,24855,0,0 TA-00000215,REF-0009,Hydrogen Plant,Planned Turnaround,2021-01-23,26,30,12.58,0.508,40525,0,1 TA-00000216,REF-0002,Hydrotreating,Pitstop,2028-12-05,9,11,17.84,0.901,95724,0,0 TA-00000217,REF-0008,Alkylation,Pitstop,2023-05-30,9,10,7.87,0.656,7720,1,0 TA-00000218,REF-0006,Hydrogen Plant,Pitstop,2024-11-14,13,16,21.26,0.572,22203,0,0 TA-00000219,REF-0013,Utilities,Planned Turnaround,2020-01-09,24,28,15.1,0.577,65191,0,0 TA-00000220,REF-0007,Cooling Water,Major Turnaround,2023-09-18,25,27,4.9,0.564,64292,0,0 TA-00000221,REF-0003,Delayed Coker,Pitstop,2027-09-26,14,16,13.14,0.692,41285,0,0 TA-00000222,REF-0015,FCCU,Emergency Shutdown,2026-04-18,8,9,7.19,0.169,76203,0,1 TA-00000223,REF-0003,FCCU,Pitstop,2024-05-18,9,11,12.5,0.98,38889,1,0 TA-00000224,REF-0008,Cooling Water,Regulatory Outage,2025-08-23,22,26,14.8,0.485,44725,1,0 TA-00000225,REF-0015,Flare System,Planned Turnaround,2023-08-25,32,35,8.41,0.492,123105,0,1 TA-00000226,REF-0006,Flare System,Pitstop,2019-11-22,7,9,14.4,0.669,95727,0,0 TA-00000227,REF-0003,Flare System,Planned Turnaround,2026-12-22,24,27,8.8,0.575,167267,0,0 TA-00000228,REF-0008,CDU,Pitstop,2021-12-06,4,5,13.15,0.591,11088,0,0 TA-00000229,REF-0001,Tank Farm,Emergency Shutdown,2019-02-21,6,8,17.74,0.712,101770,0,0 TA-00000230,REF-0004,Tank Farm,Regulatory Outage,2023-04-19,16,19,12.67,0.529,17989,1,1 TA-00000231,REF-0004,Hydrocracker,Regulatory Outage,2025-12-23,11,13,9.09,0.564,45520,1,0 TA-00000232,REF-0004,Hydrogen Plant,Planned Turnaround,2023-02-17,15,18,17.22,0.67,40957,0,0 TA-00000233,REF-0005,VDU,Planned Turnaround,2027-02-01,25,28,9.99,0.91,11789,0,0 TA-00000234,REF-0001,Hydrocracker,Planned Turnaround,2028-05-21,28,31,9.95,0.69,142505,0,0 TA-00000235,REF-0005,Delayed Coker,Planned Turnaround,2022-08-12,20,23,10.55,0.938,39069,0,0 TA-00000236,REF-0002,VDU,Emergency Shutdown,2020-02-01,7,9,14.7,0.906,72305,0,0 TA-00000237,REF-0001,Hydrocracker,Major Turnaround,2021-10-23,28,35,21.52,0.632,149921,1,0 TA-00000238,REF-0014,Sulfur Recovery,Planned Turnaround,2027-11-03,33,36,6.89,0.709,26759,1,0 TA-00000239,REF-0007,Sulfur Recovery,Planned Turnaround,2026-10-21,28,34,18.74,0.708,139785,0,0 TA-00000240,REF-0001,Reformer,Planned Turnaround,2027-03-07,21,24,9.75,0.701,157198,0,0 TA-00000241,REF-0003,Cooling Water,Planned Turnaround,2024-12-02,5,6,13.28,0.732,161462,0,0 TA-00000242,REF-0007,Hydrocracker,Planned Turnaround,2022-09-24,34,41,18.1,0.98,81185,0,0 TA-00000243,REF-0002,Alkylation,Major Turnaround,2028-09-11,37,42,11.06,0.813,95146,0,0 TA-00000244,REF-0006,Hydrocracker,Major Turnaround,2024-01-17,37,40,5.78,0.616,42852,0,0 TA-00000245,REF-0009,Alkylation,Pitstop,2026-06-09,10,11,2.74,0.338,13319,0,0 TA-00000246,REF-0015,Delayed Coker,Regulatory Outage,2021-01-10,23,26,11.86,0.667,63461,1,0 TA-00000247,REF-0013,Hydrocracker,Planned Turnaround,2027-09-05,12,14,12.43,0.6,16412,0,0 TA-00000248,REF-0004,FCCU,Pitstop,2027-01-31,9,11,14.44,0.695,66547,0,0 TA-00000249,REF-0013,Hydrotreating,Planned Turnaround,2021-01-01,34,36,5.76,0.911,84775,0,0 TA-00000250,REF-0006,Hydrocracker,Major Turnaround,2023-08-02,40,46,13.62,0.571,25843,0,0 TA-00000251,REF-0003,Hydrogen Plant,Planned Turnaround,2026-06-14,33,35,5.22,0.712,17137,0,0 TA-00000252,REF-0003,VDU,Major Turnaround,2020-09-17,54,63,15.68,0.708,142388,0,0 TA-00000253,REF-0013,CDU,Planned Turnaround,2028-12-10,32,35,7.82,0.861,42948,0,0 TA-00000254,REF-0005,Delayed Coker,Planned Turnaround,2020-01-18,16,19,18.63,0.7,88806,0,1 TA-00000255,REF-0012,VDU,Planned Turnaround,2023-09-14,27,30,8.8,0.256,18719,1,0 TA-00000256,REF-0008,Flare System,Planned Turnaround,2025-05-08,22,26,15.83,0.263,47906,0,0 TA-00000257,REF-0005,Hydrotreating,Planned Turnaround,2028-12-10,25,30,16.25,0.701,37972,1,0 TA-00000258,REF-0001,Reformer,Planned Turnaround,2028-08-21,33,37,11.92,0.79,148577,0,0 TA-00000259,REF-0002,Utilities,Planned Turnaround,2020-12-25,28,32,11.08,0.76,36361,0,0 TA-00000260,REF-0014,CDU,Major Turnaround,2027-02-01,23,24,3.91,0.743,31242,1,0 TA-00000261,REF-0003,Hydrocracker,Planned Turnaround,2022-10-04,35,51,43.98,0.761,113811,0,0 TA-00000262,REF-0004,Hydrotreating,Planned Turnaround,2020-03-15,38,51,33.85,0.514,18329,1,0 TA-00000263,REF-0004,Sulfur Recovery,Planned Turnaround,2024-06-28,26,31,18.56,0.98,73103,0,1 TA-00000264,REF-0007,FCCU,Planned Turnaround,2019-03-01,28,31,10.31,0.478,50082,0,0 TA-00000265,REF-0011,Flare System,Planned Turnaround,2026-06-27,20,23,14.85,0.731,101640,0,0 TA-00000266,REF-0014,Alkylation,Emergency Shutdown,2020-06-14,5,6,10.21,0.719,36165,0,0 TA-00000267,REF-0003,Alkylation,Planned Turnaround,2022-06-24,24,26,7.91,0.615,147356,0,0 TA-00000268,REF-0015,Utilities,Pitstop,2019-08-19,14,16,7.98,0.952,66771,0,0 TA-00000269,REF-0003,Flare System,Regulatory Outage,2026-05-12,18,21,16.09,0.696,33172,1,0 TA-00000270,REF-0011,CDU,Planned Turnaround,2026-06-15,30,34,12.0,0.643,125023,0,1 TA-00000271,REF-0011,Delayed Coker,Planned Turnaround,2024-10-22,24,28,13.88,0.759,46236,0,0 TA-00000272,REF-0002,Reformer,Planned Turnaround,2025-07-15,25,29,14.62,0.793,104851,0,0 TA-00000273,REF-0012,Reformer,Planned Turnaround,2021-11-19,33,53,57.83,0.471,54123,0,0 TA-00000274,REF-0015,Sulfur Recovery,Major Turnaround,2028-09-04,21,24,12.83,0.452,113865,0,0 TA-00000275,REF-0008,Sulfur Recovery,Pitstop,2022-08-18,11,13,9.41,0.616,54752,0,0 TA-00000276,REF-0001,Tank Farm,Major Turnaround,2028-12-08,33,41,22.21,0.557,108815,0,1 TA-00000277,REF-0013,Hydrocracker,Planned Turnaround,2024-06-09,22,26,15.73,0.675,59162,0,0 TA-00000278,REF-0001,Tank Farm,Planned Turnaround,2019-06-25,33,39,16.09,0.817,67947,0,0 TA-00000279,REF-0001,CDU,Pitstop,2021-05-28,12,14,8.44,0.843,68875,0,0 TA-00000280,REF-0005,Hydrotreating,Planned Turnaround,2025-12-18,23,27,16.57,0.653,105380,0,0 TA-00000281,REF-0013,Hydrocracker,Major Turnaround,2022-08-28,41,45,7.33,0.645,83534,0,0 TA-00000282,REF-0012,Hydrotreating,Pitstop,2025-04-03,6,7,12.92,0.493,128488,0,0 TA-00000283,REF-0007,Reformer,Planned Turnaround,2022-11-19,41,46,10.8,0.749,130895,0,1 TA-00000284,REF-0012,Sulfur Recovery,Planned Turnaround,2019-07-04,22,25,11.58,0.98,51000,0,0 TA-00000285,REF-0013,Flare System,Planned Turnaround,2025-09-20,17,20,15.68,0.98,61112,0,1 TA-00000286,REF-0007,Sulfur Recovery,Planned Turnaround,2019-01-16,33,38,14.32,0.5,146385,0,1 TA-00000287,REF-0001,Hydrotreating,Planned Turnaround,2024-08-28,33,38,15.11,0.731,155620,0,1 TA-00000288,REF-0012,Flare System,Planned Turnaround,2022-03-31,20,22,9.55,0.356,24802,0,0 TA-00000289,REF-0008,Hydrotreating,Major Turnaround,2020-04-07,32,36,10.07,0.609,53715,0,0 TA-00000290,REF-0007,Cooling Water,Planned Turnaround,2026-05-21,28,33,15.1,0.819,103685,0,0 TA-00000291,REF-0003,Sulfur Recovery,Emergency Shutdown,2023-02-15,5,6,9.36,0.513,43498,0,0 TA-00000292,REF-0012,Hydrogen Plant,Planned Turnaround,2025-10-10,23,27,16.06,0.682,88058,0,0 TA-00000293,REF-0006,Hydrogen Plant,Planned Turnaround,2020-10-29,21,23,8.0,0.697,74360,1,0 TA-00000294,REF-0005,FCCU,Major Turnaround,2021-02-23,56,62,10.56,0.917,30377,0,0 TA-00000295,REF-0005,Delayed Coker,Planned Turnaround,2021-02-15,34,37,7.83,0.52,69595,0,0 TA-00000296,REF-0013,Hydrocracker,Major Turnaround,2026-08-25,26,30,13.97,0.647,99827,0,0 TA-00000297,REF-0011,FCCU,Major Turnaround,2027-12-06,48,55,12.77,0.475,46095,1,1 TA-00000298,REF-0012,Flare System,Planned Turnaround,2025-02-01,35,40,13.18,0.584,155536,0,1 TA-00000299,REF-0002,CDU,Planned Turnaround,2027-03-19,21,26,19.26,0.482,122561,0,0 TA-00000300,REF-0010,Hydrotreating,Major Turnaround,2027-08-02,31,38,21.8,0.924,65297,1,0 TA-00000301,REF-0001,Sulfur Recovery,Planned Turnaround,2022-01-14,17,18,0.33,0.947,85934,0,0 TA-00000302,REF-0008,Tank Farm,Planned Turnaround,2024-08-21,29,30,0.13,0.824,48832,0,0 TA-00000303,REF-0001,Sulfur Recovery,Emergency Shutdown,2020-08-31,7,8,10.99,0.751,98675,0,0 TA-00000304,REF-0006,Delayed Coker,Regulatory Outage,2023-12-27,18,20,8.22,0.593,31079,1,1 TA-00000305,REF-0015,Alkylation,Planned Turnaround,2025-04-15,29,33,13.63,0.405,77423,0,0 TA-00000306,REF-0005,Hydrotreating,Emergency Shutdown,2027-09-24,8,9,9.77,0.64,68714,0,1 TA-00000307,REF-0004,Alkylation,Planned Turnaround,2022-03-13,26,29,10.88,0.268,23958,0,0 TA-00000308,REF-0006,Utilities,Planned Turnaround,2024-11-15,31,34,7.15,0.51,55470,0,0 TA-00000309,REF-0007,Cooling Water,Pitstop,2019-05-29,11,13,12.79,0.252,36146,0,0 TA-00000310,REF-0003,Utilities,Planned Turnaround,2024-12-16,28,30,5.24,0.759,145561,0,0 TA-00000311,REF-0003,Hydrocracker,Planned Turnaround,2021-05-12,17,20,13.46,0.586,147890,0,0 TA-00000312,REF-0009,Hydrocracker,Planned Turnaround,2019-08-12,25,28,9.86,0.679,18098,0,0 TA-00000313,REF-0003,Hydrotreating,Planned Turnaround,2019-03-15,19,23,20.18,0.556,138031,0,0 TA-00000314,REF-0006,Reformer,Emergency Shutdown,2026-11-06,8,9,5.47,0.588,29809,0,0 TA-00000315,REF-0004,VDU,Major Turnaround,2021-12-01,45,47,2.93,0.638,68400,1,0 TA-00000316,REF-0015,Cooling Water,Major Turnaround,2024-01-12,48,57,16.95,0.585,157874,0,0 TA-00000317,REF-0006,FCCU,Planned Turnaround,2020-01-06,27,30,10.47,0.98,48291,0,0 TA-00000318,REF-0012,CDU,Planned Turnaround,2025-06-21,18,20,9.59,0.624,35157,0,0 TA-00000319,REF-0012,VDU,Planned Turnaround,2021-02-21,21,25,15.57,0.558,77309,0,0 TA-00000320,REF-0009,Flare System,Planned Turnaround,2026-06-02,27,31,11.19,0.63,77766,0,0 TA-00000321,REF-0004,Tank Farm,Regulatory Outage,2021-07-15,20,23,13.26,0.573,51759,1,0 TA-00000322,REF-0015,Hydrocracker,Emergency Shutdown,2028-03-04,8,9,4.29,0.602,159631,0,0 TA-00000323,REF-0001,FCCU,Planned Turnaround,2023-02-16,18,22,17.81,0.433,33044,0,0 TA-00000324,REF-0010,Tank Farm,Planned Turnaround,2021-04-05,25,28,10.98,0.915,35933,0,0 TA-00000325,REF-0010,Tank Farm,Regulatory Outage,2027-10-21,18,20,6.72,0.797,26818,1,0 TA-00000326,REF-0011,Flare System,Pitstop,2022-09-04,14,16,11.81,0.529,64509,0,0 TA-00000327,REF-0006,Delayed Coker,Planned Turnaround,2024-07-03,29,32,7.66,0.612,88544,0,0 TA-00000328,REF-0001,Sulfur Recovery,Regulatory Outage,2028-04-09,24,26,5.58,0.634,115107,1,0 TA-00000329,REF-0014,Delayed Coker,Planned Turnaround,2019-04-09,17,24,40.91,0.516,19761,0,0 TA-00000330,REF-0002,Sulfur Recovery,Major Turnaround,2022-07-25,26,31,15.77,0.971,53567,0,0 TA-00000331,REF-0005,Hydrotreating,Planned Turnaround,2028-02-12,35,42,17.38,0.98,56302,1,1 TA-00000332,REF-0009,Sulfur Recovery,Emergency Shutdown,2021-10-23,6,7,10.42,0.383,22690,0,0 TA-00000333,REF-0011,CDU,Major Turnaround,2028-04-20,48,57,17.42,0.662,130343,0,0 TA-00000334,REF-0009,Reformer,Planned Turnaround,2025-06-30,29,33,11.69,0.8,77830,0,0 TA-00000335,REF-0014,Hydrotreating,Planned Turnaround,2027-12-27,30,35,13.39,0.562,53004,0,0 TA-00000336,REF-0008,CDU,Planned Turnaround,2024-07-08,30,35,15.53,0.794,64340,1,0 TA-00000337,REF-0012,Utilities,Major Turnaround,2022-12-19,53,61,14.48,0.441,52982,0,0 TA-00000338,REF-0006,Reformer,Planned Turnaround,2027-08-22,13,15,15.12,0.767,98593,0,0 TA-00000339,REF-0010,Tank Farm,Major Turnaround,2028-08-08,47,52,10.21,0.671,42327,0,0 TA-00000340,REF-0006,Sulfur Recovery,Planned Turnaround,2026-06-05,24,28,13.46,0.571,79885,0,0 TA-00000341,REF-0010,Flare System,Planned Turnaround,2025-07-03,26,31,15.83,0.876,44603,0,0 TA-00000342,REF-0009,Tank Farm,Regulatory Outage,2021-06-09,20,24,16.98,0.738,17952,1,0 TA-00000343,REF-0015,Flare System,Major Turnaround,2026-01-09,22,25,12.15,0.612,95769,0,0 TA-00000344,REF-0014,Flare System,Planned Turnaround,2019-07-11,20,23,11.08,0.854,14178,0,0 TA-00000345,REF-0013,Hydrogen Plant,Planned Turnaround,2023-10-24,25,27,5.76,0.809,86432,0,0 TA-00000346,REF-0008,Utilities,Pitstop,2025-07-19,7,8,5.74,0.74,45323,0,0 TA-00000347,REF-0002,Hydrocracker,Regulatory Outage,2026-03-23,21,23,8.85,0.765,101647,1,0 TA-00000348,REF-0011,CDU,Regulatory Outage,2020-11-24,13,15,7.9,0.617,125053,1,0 TA-00000349,REF-0014,FCCU,Planned Turnaround,2022-10-16,30,32,3.93,0.471,25981,0,0 TA-00000350,REF-0013,Utilities,Major Turnaround,2019-06-10,38,45,18.38,0.745,100177,1,0 TA-00000351,REF-0003,VDU,Planned Turnaround,2022-12-03,23,26,9.46,0.834,31578,0,0 TA-00000352,REF-0005,Delayed Coker,Planned Turnaround,2028-09-03,24,26,6.55,0.729,13232,0,0 TA-00000353,REF-0011,Sulfur Recovery,Planned Turnaround,2021-01-18,26,30,13.85,0.938,93760,0,0 TA-00000354,REF-0002,Cooling Water,Planned Turnaround,2028-08-21,29,33,12.62,0.474,20879,0,0 TA-00000355,REF-0011,Hydrogen Plant,Major Turnaround,2026-06-28,19,22,12.79,0.422,15568,0,1 TA-00000356,REF-0004,Alkylation,Planned Turnaround,2020-04-17,21,24,10.8,0.722,28892,0,0 TA-00000357,REF-0010,FCCU,Planned Turnaround,2024-06-11,22,24,8.84,0.522,33190,0,0 TA-00000358,REF-0013,Tank Farm,Major Turnaround,2026-09-23,30,33,7.16,0.499,25590,0,0 TA-00000359,REF-0007,Hydrocracker,Planned Turnaround,2028-11-26,27,32,18.33,0.565,109123,0,0 TA-00000360,REF-0010,VDU,Planned Turnaround,2020-06-12,19,22,11.66,0.337,75229,1,0 TA-00000361,REF-0014,Reformer,Planned Turnaround,2023-11-07,24,29,17.6,0.545,18952,0,0 TA-00000362,REF-0014,FCCU,Major Turnaround,2022-08-09,41,45,7.73,0.548,36517,0,0 TA-00000363,REF-0001,Utilities,Planned Turnaround,2021-06-18,29,35,19.87,0.751,122019,1,0 TA-00000364,REF-0001,Delayed Coker,Planned Turnaround,2025-01-30,26,29,8.98,0.279,116281,0,0 TA-00000365,REF-0015,Sulfur Recovery,Planned Turnaround,2021-10-11,18,20,9.59,0.266,56474,0,0 TA-00000366,REF-0013,Hydrogen Plant,Pitstop,2028-02-03,7,9,17.68,0.69,80907,0,0 TA-00000367,REF-0013,Delayed Coker,Planned Turnaround,2026-05-09,29,33,13.45,0.742,53337,0,1 TA-00000368,REF-0014,CDU,Planned Turnaround,2023-03-14,11,12,4.74,0.752,35745,0,0 TA-00000369,REF-0014,Hydrogen Plant,Planned Turnaround,2028-11-23,28,33,17.34,0.812,54831,0,1 TA-00000370,REF-0011,Hydrotreating,Major Turnaround,2025-05-29,33,36,7.37,0.698,50085,0,0 TA-00000371,REF-0001,Hydrotreating,Regulatory Outage,2021-09-19,14,17,19.13,0.98,51205,1,0 TA-00000372,REF-0008,Cooling Water,Planned Turnaround,2022-09-16,30,36,18.98,0.466,64347,0,0 TA-00000373,REF-0005,Flare System,Planned Turnaround,2019-07-13,39,49,24.98,0.98,91320,0,0 TA-00000374,REF-0003,CDU,Planned Turnaround,2022-08-29,26,30,12.17,0.372,158585,1,0 TA-00000375,REF-0007,Reformer,Major Turnaround,2022-11-05,53,59,10.75,0.657,81287,0,0 TA-00000376,REF-0014,Hydrotreating,Major Turnaround,2027-06-29,52,55,5.42,0.869,13658,0,0 TA-00000377,REF-0007,Flare System,Planned Turnaround,2020-01-01,32,38,16.06,0.756,70500,0,0 TA-00000378,REF-0009,Flare System,Major Turnaround,2028-08-29,24,27,12.09,0.5,70411,0,0 TA-00000379,REF-0003,Sulfur Recovery,Planned Turnaround,2022-11-09,18,21,13.29,0.594,29212,0,0 TA-00000380,REF-0013,Alkylation,Pitstop,2023-05-05,12,14,12.26,0.679,64825,0,0 TA-00000381,REF-0001,Hydrotreating,Planned Turnaround,2025-05-15,20,24,18.14,0.961,149855,0,0 TA-00000382,REF-0006,FCCU,Planned Turnaround,2024-12-30,25,28,10.86,0.735,17367,0,0 TA-00000383,REF-0014,Hydrocracker,Planned Turnaround,2024-07-20,30,31,2.95,0.471,39388,0,0 TA-00000384,REF-0013,Reformer,Regulatory Outage,2024-05-28,21,24,11.85,0.605,83456,1,0 TA-00000385,REF-0008,CDU,Major Turnaround,2028-08-31,46,53,13.65,0.757,17416,0,0 TA-00000386,REF-0009,VDU,Planned Turnaround,2020-03-07,25,29,13.13,0.842,73399,0,1 TA-00000387,REF-0008,FCCU,Pitstop,2022-01-22,11,14,18.23,0.892,64196,0,0 TA-00000388,REF-0001,Sulfur Recovery,Planned Turnaround,2020-07-27,30,35,14.35,0.782,40293,0,0 TA-00000389,REF-0013,Tank Farm,Major Turnaround,2027-05-20,57,62,7.37,0.505,80798,0,1 TA-00000390,REF-0003,Sulfur Recovery,Major Turnaround,2025-08-10,41,46,12.08,0.64,110847,0,0 TA-00000391,REF-0013,CDU,Planned Turnaround,2024-09-30,27,33,19.39,0.748,31513,0,0 TA-00000392,REF-0006,Flare System,Planned Turnaround,2025-03-17,31,34,8.07,0.631,38690,0,0 TA-00000393,REF-0012,Utilities,Planned Turnaround,2021-04-30,31,36,13.06,0.719,67877,0,0 TA-00000394,REF-0002,FCCU,Major Turnaround,2024-05-09,68,74,8.09,0.447,120809,0,0 TA-00000395,REF-0007,Hydrotreating,Emergency Shutdown,2023-02-04,8,12,39.22,0.678,121597,0,0 TA-00000396,REF-0015,CDU,Major Turnaround,2027-11-21,39,47,18.17,0.498,142081,0,0 TA-00000397,REF-0004,CDU,Planned Turnaround,2026-02-10,26,29,9.11,0.451,50932,0,0 TA-00000398,REF-0015,VDU,Major Turnaround,2020-11-16,47,47,0.0,0.559,37995,0,0 TA-00000399,REF-0005,Sulfur Recovery,Pitstop,2026-10-29,7,8,11.34,0.534,17034,0,0 TA-00000400,REF-0009,Sulfur Recovery,Planned Turnaround,2019-02-03,22,25,9.34,0.669,73562,0,0 TA-00000401,REF-0009,Cooling Water,Major Turnaround,2028-06-10,44,49,10.54,0.641,55074,0,0 TA-00000402,REF-0015,Sulfur Recovery,Emergency Shutdown,2025-09-16,5,6,12.07,0.313,28710,0,0 TA-00000403,REF-0005,VDU,Planned Turnaround,2019-06-23,18,20,9.69,0.756,91639,0,0 TA-00000404,REF-0010,Reformer,Planned Turnaround,2023-06-20,21,24,12.61,0.847,43053,0,0 TA-00000405,REF-0009,Reformer,Pitstop,2027-11-27,14,16,14.1,0.497,52736,0,0 TA-00000406,REF-0003,FCCU,Planned Turnaround,2022-12-07,29,34,15.48,0.488,30496,0,0 TA-00000407,REF-0007,Flare System,Planned Turnaround,2021-04-01,22,25,11.06,0.644,136337,0,1 TA-00000408,REF-0011,Hydrocracker,Major Turnaround,2024-08-01,33,39,15.37,0.804,127254,0,0 TA-00000409,REF-0015,FCCU,Planned Turnaround,2023-02-02,14,15,6.13,0.872,160103,1,0 TA-00000410,REF-0001,Hydrogen Plant,Planned Turnaround,2020-03-08,27,30,11.01,0.646,129168,0,0 TA-00000411,REF-0014,CDU,Planned Turnaround,2024-04-08,25,30,16.66,0.423,27427,0,0 TA-00000412,REF-0015,Sulfur Recovery,Planned Turnaround,2023-08-05,25,34,32.43,0.445,43623,1,0 TA-00000413,REF-0010,Tank Farm,Major Turnaround,2020-07-26,41,44,6.96,0.93,83124,0,0 TA-00000414,REF-0003,Hydrocracker,Regulatory Outage,2028-06-30,19,21,7.1,0.834,24861,1,0 TA-00000415,REF-0003,Flare System,Planned Turnaround,2022-07-21,27,42,52.97,0.467,133509,0,0 TA-00000416,REF-0006,VDU,Planned Turnaround,2020-05-25,20,21,1.68,0.489,33958,0,0 TA-00000417,REF-0010,VDU,Planned Turnaround,2024-03-28,30,35,16.39,0.427,43423,0,0 TA-00000418,REF-0006,Utilities,Planned Turnaround,2019-01-24,19,20,4.6,0.442,56928,0,0 TA-00000419,REF-0004,Flare System,Planned Turnaround,2023-03-03,22,26,14.45,0.684,78618,1,0 TA-00000420,REF-0012,Alkylation,Major Turnaround,2025-04-22,52,60,14.69,0.4,49622,0,0 TA-00000421,REF-0001,Hydrocracker,Emergency Shutdown,2020-05-26,9,11,12.44,0.576,120594,1,0 TA-00000422,REF-0012,Reformer,Planned Turnaround,2022-02-26,15,18,15.54,0.756,24910,0,0 TA-00000423,REF-0006,VDU,Major Turnaround,2022-05-23,41,44,6.01,0.481,61536,0,0 TA-00000424,REF-0008,Tank Farm,Planned Turnaround,2020-03-18,30,34,12.33,0.568,63813,0,0 TA-00000425,REF-0014,Delayed Coker,Major Turnaround,2024-11-02,41,46,9.88,0.592,47515,1,0 TA-00000426,REF-0003,FCCU,Planned Turnaround,2019-07-05,32,35,7.38,0.664,36650,0,0 TA-00000427,REF-0015,Tank Farm,Planned Turnaround,2019-03-20,28,30,5.66,0.783,45383,0,0 TA-00000428,REF-0006,Sulfur Recovery,Pitstop,2020-03-15,7,9,17.27,0.612,79143,0,0 TA-00000429,REF-0004,Reformer,Planned Turnaround,2027-09-01,9,11,12.21,0.842,50259,0,0 TA-00000430,REF-0005,Hydrogen Plant,Planned Turnaround,2020-09-14,27,30,8.78,0.76,13743,0,0 TA-00000431,REF-0015,CDU,Planned Turnaround,2023-04-02,20,24,15.1,0.482,136439,0,0 TA-00000432,REF-0013,Flare System,Pitstop,2027-07-16,11,13,12.17,0.552,17817,1,0 TA-00000433,REF-0003,CDU,Planned Turnaround,2020-12-07,23,27,14.21,0.385,19228,1,0 TA-00000434,REF-0009,Alkylation,Planned Turnaround,2027-08-01,19,22,11.08,0.705,53273,0,0 TA-00000435,REF-0010,Tank Farm,Planned Turnaround,2027-11-20,17,20,12.73,0.651,88130,0,0 TA-00000436,REF-0009,Hydrotreating,Pitstop,2027-12-17,9,13,40.61,0.713,52105,0,0 TA-00000437,REF-0006,Tank Farm,Major Turnaround,2023-12-08,48,53,8.38,0.864,51142,0,0 TA-00000438,REF-0008,Utilities,Planned Turnaround,2022-10-26,30,44,44.76,0.606,62075,0,0 TA-00000439,REF-0004,Utilities,Planned Turnaround,2025-07-14,33,36,8.88,0.396,40889,0,0 TA-00000440,REF-0007,Sulfur Recovery,Planned Turnaround,2026-09-13,18,20,6.94,0.792,105226,1,0 TA-00000441,REF-0006,Sulfur Recovery,Planned Turnaround,2024-10-08,33,36,8.67,0.757,51548,0,0 TA-00000442,REF-0007,Hydrogen Plant,Planned Turnaround,2028-09-27,26,30,12.37,0.497,137836,0,0 TA-00000443,REF-0008,Delayed Coker,Planned Turnaround,2019-01-14,34,40,17.46,0.484,23805,0,0 TA-00000444,REF-0012,Utilities,Planned Turnaround,2027-08-17,13,15,13.15,0.877,94617,1,0 TA-00000445,REF-0003,VDU,Planned Turnaround,2020-10-28,35,44,24.82,0.583,80272,0,0 TA-00000446,REF-0004,CDU,Planned Turnaround,2021-02-28,20,23,13.54,0.217,34476,0,0 TA-00000447,REF-0014,Alkylation,Planned Turnaround,2019-12-27,21,24,9.86,0.473,21366,0,0 TA-00000448,REF-0010,CDU,Planned Turnaround,2025-04-30,18,21,11.82,0.691,41621,0,0 TA-00000449,REF-0006,Reformer,Planned Turnaround,2024-04-23,28,34,20.37,0.661,72287,0,0 TA-00000450,REF-0008,Hydrocracker,Pitstop,2024-12-20,12,14,11.67,0.8,19621,0,0 TA-00000451,REF-0006,Hydrogen Plant,Major Turnaround,2020-04-25,60,67,10.19,0.551,19610,0,0 TA-00000452,REF-0012,Tank Farm,Planned Turnaround,2020-09-28,33,38,13.26,0.651,128818,0,0 TA-00000453,REF-0013,Hydrogen Plant,Emergency Shutdown,2022-02-03,9,11,17.71,0.63,31377,0,0 TA-00000454,REF-0003,FCCU,Planned Turnaround,2028-02-28,26,29,10.93,0.578,103381,0,0 TA-00000455,REF-0012,Cooling Water,Pitstop,2023-01-10,12,14,16.34,0.889,122715,0,0 TA-00000456,REF-0011,Hydrotreating,Planned Turnaround,2020-09-26,25,28,10.56,0.72,49388,0,0 TA-00000457,REF-0002,VDU,Regulatory Outage,2021-05-30,12,14,8.98,0.695,125480,1,0 TA-00000458,REF-0008,Hydrocracker,Planned Turnaround,2023-10-25,33,35,6.0,0.501,34585,0,0 TA-00000459,REF-0009,Flare System,Pitstop,2026-02-23,7,8,12.17,0.713,59053,0,0 TA-00000460,REF-0013,Sulfur Recovery,Major Turnaround,2021-03-29,31,34,8.82,0.23,11785,0,0 TA-00000461,REF-0011,CDU,Planned Turnaround,2020-02-02,26,31,16.04,0.791,12681,0,0 TA-00000462,REF-0014,Flare System,Planned Turnaround,2024-09-19,25,27,7.32,0.842,52611,0,0 TA-00000463,REF-0012,Delayed Coker,Planned Turnaround,2024-10-21,34,36,5.33,0.51,41511,1,1 TA-00000464,REF-0014,Reformer,Planned Turnaround,2028-07-25,23,26,8.92,0.498,17396,0,0 TA-00000465,REF-0007,Reformer,Planned Turnaround,2023-10-08,26,30,12.26,0.225,19446,0,0 TA-00000466,REF-0003,Hydrocracker,Planned Turnaround,2024-11-20,27,31,11.39,0.749,159213,0,0 TA-00000467,REF-0005,FCCU,Planned Turnaround,2021-02-04,26,31,16.64,0.765,89259,0,0 TA-00000468,REF-0012,FCCU,Planned Turnaround,2025-11-27,22,27,18.63,0.381,99341,0,0 TA-00000469,REF-0004,Reformer,Emergency Shutdown,2019-01-22,6,7,6.14,0.867,55554,0,0 TA-00000470,REF-0008,Tank Farm,Planned Turnaround,2024-08-29,28,31,9.96,0.663,47305,0,0 TA-00000471,REF-0013,Sulfur Recovery,Planned Turnaround,2025-06-22,30,35,15.58,0.798,31885,1,0 TA-00000472,REF-0008,FCCU,Regulatory Outage,2026-11-08,17,19,7.6,0.729,72237,1,0 TA-00000473,REF-0009,VDU,Planned Turnaround,2025-02-06,18,23,24.68,0.66,74152,0,0 TA-00000474,REF-0010,Flare System,Pitstop,2019-08-04,8,9,8.87,0.67,60097,0,1 TA-00000475,REF-0008,Flare System,Planned Turnaround,2027-07-11,17,19,11.02,0.581,42461,0,0 TA-00000476,REF-0015,Delayed Coker,Planned Turnaround,2019-01-10,12,14,15.0,0.671,29669,0,0 TA-00000477,REF-0013,Hydrogen Plant,Emergency Shutdown,2025-07-21,6,7,13.35,0.82,89643,0,0 TA-00000478,REF-0009,Cooling Water,Pitstop,2019-05-25,10,12,11.77,0.735,33113,0,0 TA-00000479,REF-0014,Hydrogen Plant,Emergency Shutdown,2027-02-14,7,9,18.13,0.73,37780,0,0 TA-00000480,REF-0013,Delayed Coker,Emergency Shutdown,2022-05-30,8,10,12.94,0.56,69354,0,0 TA-00000481,REF-0003,Cooling Water,Planned Turnaround,2019-04-17,20,23,12.58,0.491,56635,0,0 TA-00000482,REF-0003,Flare System,Pitstop,2025-03-04,11,12,8.62,0.602,74854,0,0 TA-00000483,REF-0012,VDU,Planned Turnaround,2022-01-04,13,14,4.51,0.903,155709,0,0 TA-00000484,REF-0015,Hydrogen Plant,Planned Turnaround,2023-03-10,24,28,12.92,0.77,150752,0,0 TA-00000485,REF-0006,CDU,Planned Turnaround,2021-06-15,29,32,7.01,0.36,37863,0,0 TA-00000486,REF-0013,Hydrogen Plant,Planned Turnaround,2028-09-03,24,28,15.1,0.674,103333,0,1 TA-00000487,REF-0010,CDU,Planned Turnaround,2027-05-11,26,30,13.34,0.766,88057,0,0 TA-00000488,REF-0002,Hydrogen Plant,Major Turnaround,2027-08-15,55,63,12.77,0.754,110788,0,0 TA-00000489,REF-0005,Cooling Water,Planned Turnaround,2019-01-27,23,27,15.64,0.733,12849,0,0 TA-00000490,REF-0007,Tank Farm,Planned Turnaround,2023-04-17,15,16,2.41,0.425,87908,0,0 TA-00000491,REF-0015,Cooling Water,Pitstop,2027-07-22,11,12,8.68,0.559,127809,0,0 TA-00000492,REF-0015,FCCU,Pitstop,2020-04-02,7,8,10.16,0.899,25238,0,0 TA-00000493,REF-0013,FCCU,Planned Turnaround,2021-01-28,25,28,11.23,0.689,15236,0,1 TA-00000494,REF-0001,Alkylation,Planned Turnaround,2026-10-07,31,34,8.17,0.529,147354,0,0 TA-00000495,REF-0011,VDU,Pitstop,2020-02-12,10,12,13.44,0.414,61366,0,0 TA-00000496,REF-0003,Delayed Coker,Major Turnaround,2024-10-11,42,45,6.5,0.567,171347,0,0 TA-00000497,REF-0013,Cooling Water,Pitstop,2024-07-19,13,16,15.97,0.15,50767,0,0 TA-00000498,REF-0001,Hydrotreating,Planned Turnaround,2024-09-04,18,22,18.22,0.668,38841,0,0 TA-00000499,REF-0015,Hydrotreating,Planned Turnaround,2022-05-19,27,31,11.29,0.88,127215,0,0 TA-00000500,REF-0003,Utilities,Planned Turnaround,2024-12-22,26,29,10.98,0.98,137362,0,0 TA-00000501,REF-0001,FCCU,Planned Turnaround,2023-09-16,27,31,13.66,0.839,72551,0,0 TA-00000502,REF-0010,Alkylation,Planned Turnaround,2021-03-15,24,27,9.37,0.525,43090,1,0 TA-00000503,REF-0008,Cooling Water,Planned Turnaround,2021-10-24,26,28,7.58,0.582,34012,1,0 TA-00000504,REF-0004,Cooling Water,Planned Turnaround,2023-11-07,28,31,8.36,0.549,62038,1,0 TA-00000505,REF-0009,Flare System,Emergency Shutdown,2022-02-11,5,6,4.68,0.851,52060,0,0 TA-00000506,REF-0005,FCCU,Emergency Shutdown,2028-07-14,5,6,7.43,0.814,52954,0,0 TA-00000507,REF-0004,Hydrocracker,Emergency Shutdown,2025-05-24,9,11,11.41,0.66,57366,1,0 TA-00000508,REF-0008,Sulfur Recovery,Planned Turnaround,2027-02-17,16,18,11.78,0.742,32784,0,0 TA-00000509,REF-0011,Alkylation,Major Turnaround,2019-01-26,55,66,18.5,0.348,123176,0,0 TA-00000510,REF-0004,Alkylation,Pitstop,2028-02-24,7,8,11.18,0.645,31224,1,0 TA-00000511,REF-0004,Hydrotreating,Planned Turnaround,2025-03-01,28,32,13.49,0.479,55196,0,0 TA-00000512,REF-0014,Hydrocracker,Planned Turnaround,2024-07-11,22,27,20.98,0.605,38200,0,0 TA-00000513,REF-0010,Cooling Water,Planned Turnaround,2026-07-18,29,36,20.97,0.497,60437,0,0 TA-00000514,REF-0007,Hydrogen Plant,Planned Turnaround,2019-04-06,27,31,14.42,0.701,132687,0,0 TA-00000515,REF-0007,Reformer,Planned Turnaround,2026-10-17,21,25,15.84,0.614,14718,0,0 TA-00000516,REF-0014,Delayed Coker,Planned Turnaround,2019-09-07,21,25,15.48,0.638,9282,0,0 TA-00000517,REF-0010,Utilities,Pitstop,2028-01-16,13,15,12.4,0.687,14496,0,0 TA-00000518,REF-0012,Hydrogen Plant,Planned Turnaround,2023-03-06,19,23,16.44,0.803,114239,1,0 TA-00000519,REF-0004,Sulfur Recovery,Major Turnaround,2020-07-18,67,78,16.0,0.98,54533,1,0 TA-00000520,REF-0004,FCCU,Planned Turnaround,2020-01-17,26,30,12.98,0.471,11970,0,0 TA-00000521,REF-0010,FCCU,Regulatory Outage,2024-10-29,21,24,12.18,0.635,32858,1,0 TA-00000522,REF-0007,Tank Farm,Emergency Shutdown,2021-04-30,9,11,11.61,0.479,143650,0,0 TA-00000523,REF-0014,Tank Farm,Pitstop,2022-07-24,9,11,19.25,0.595,49055,0,0 TA-00000524,REF-0009,FCCU,Planned Turnaround,2028-01-24,34,38,11.51,0.442,46045,0,0 TA-00000525,REF-0015,Hydrotreating,Planned Turnaround,2027-07-30,11,12,6.02,0.889,76819,0,0 TA-00000526,REF-0003,Hydrocracker,Planned Turnaround,2021-09-06,38,42,9.92,0.575,33769,0,1 TA-00000527,REF-0004,FCCU,Planned Turnaround,2023-11-16,18,21,15.95,0.508,18138,0,0 TA-00000528,REF-0007,Utilities,Planned Turnaround,2028-06-26,38,40,2.82,0.736,52010,0,0 TA-00000529,REF-0013,Hydrogen Plant,Planned Turnaround,2028-07-04,26,28,4.32,0.809,102897,0,1 TA-00000530,REF-0014,Alkylation,Planned Turnaround,2019-10-20,23,28,19.45,0.52,7324,0,0 TA-00000531,REF-0012,CDU,Pitstop,2027-09-22,11,13,10.33,0.374,95909,0,0 TA-00000532,REF-0003,Flare System,Planned Turnaround,2028-11-09,30,34,11.22,0.447,30870,0,0 TA-00000533,REF-0001,Reformer,Major Turnaround,2028-12-18,50,55,9.23,0.747,118983,1,0 TA-00000534,REF-0003,Cooling Water,Pitstop,2023-07-06,12,14,9.67,0.783,26747,0,1 TA-00000535,REF-0001,Hydrogen Plant,Major Turnaround,2027-09-05,51,62,20.75,0.834,115021,0,1 TA-00000536,REF-0001,Hydrogen Plant,Planned Turnaround,2021-03-29,20,22,5.08,0.503,70914,0,0 TA-00000537,REF-0001,Flare System,Planned Turnaround,2026-02-06,20,23,12.54,0.584,114230,0,0 TA-00000538,REF-0014,Hydrogen Plant,Planned Turnaround,2028-07-21,28,32,13.98,0.785,49458,0,0 TA-00000539,REF-0015,Utilities,Major Turnaround,2027-06-21,44,46,3.28,0.703,54144,0,0 TA-00000540,REF-0001,Sulfur Recovery,Major Turnaround,2024-03-08,48,56,15.9,0.844,92969,1,0 TA-00000541,REF-0008,Utilities,Planned Turnaround,2023-08-21,33,38,14.78,0.967,25988,1,0 TA-00000542,REF-0012,Delayed Coker,Planned Turnaround,2027-07-23,23,25,8.09,0.614,124107,0,0 TA-00000543,REF-0004,Sulfur Recovery,Planned Turnaround,2023-08-15,20,23,10.46,0.607,15085,0,0 TA-00000544,REF-0002,Reformer,Major Turnaround,2028-06-09,25,29,12.88,0.517,86624,0,0 TA-00000545,REF-0009,Hydrocracker,Planned Turnaround,2027-06-12,24,28,13.08,0.98,69885,1,1 TA-00000546,REF-0008,CDU,Planned Turnaround,2022-07-11,30,33,7.77,0.243,83219,0,0 TA-00000547,REF-0007,Sulfur Recovery,Regulatory Outage,2020-07-11,10,12,10.28,0.717,108912,1,0 TA-00000548,REF-0001,Hydrogen Plant,Planned Turnaround,2028-12-14,23,27,14.68,0.718,67085,0,0 TA-00000549,REF-0006,Reformer,Planned Turnaround,2023-11-12,22,26,15.07,0.562,19741,0,0 TA-00000550,REF-0006,Flare System,Planned Turnaround,2028-11-14,31,36,14.65,0.502,71229,1,0 TA-00000551,REF-0004,Cooling Water,Planned Turnaround,2022-09-05,27,32,15.58,0.98,38552,0,0 TA-00000552,REF-0010,Delayed Coker,Regulatory Outage,2019-08-08,22,25,11.75,0.467,11457,1,0 TA-00000553,REF-0007,Reformer,Major Turnaround,2022-08-31,56,63,11.01,0.98,14142,1,0 TA-00000554,REF-0009,Alkylation,Planned Turnaround,2028-11-21,25,29,12.57,0.941,55677,0,1 TA-00000555,REF-0010,Cooling Water,Planned Turnaround,2028-03-26,27,34,22.58,0.723,75668,0,0 TA-00000556,REF-0007,Delayed Coker,Pitstop,2019-03-03,6,7,14.09,0.623,115164,1,0 TA-00000557,REF-0002,Sulfur Recovery,Planned Turnaround,2024-08-20,20,22,9.37,0.493,74740,0,0 TA-00000558,REF-0003,Utilities,Planned Turnaround,2024-12-09,33,37,12.08,0.584,33762,0,0 TA-00000559,REF-0003,Utilities,Major Turnaround,2023-10-14,59,63,5.5,0.587,106451,0,0 TA-00000560,REF-0010,Reformer,Planned Turnaround,2020-09-07,22,24,7.43,0.547,78468,0,0 TA-00000561,REF-0003,FCCU,Planned Turnaround,2028-09-08,37,41,10.52,0.777,19678,0,0 TA-00000562,REF-0001,Reformer,Regulatory Outage,2025-01-10,12,15,18.18,0.584,74885,1,0 TA-00000563,REF-0004,Utilities,Pitstop,2027-10-15,9,10,9.23,0.53,16047,0,0 TA-00000564,REF-0008,Sulfur Recovery,Planned Turnaround,2025-03-23,34,40,17.33,0.699,69192,0,0 TA-00000565,REF-0007,Utilities,Major Turnaround,2025-04-22,33,36,7.17,0.749,69881,0,0 TA-00000566,REF-0009,Delayed Coker,Planned Turnaround,2023-09-01,25,30,19.31,0.972,78301,0,0 TA-00000567,REF-0013,Hydrocracker,Pitstop,2021-09-09,11,14,21.43,0.561,17121,0,0 TA-00000568,REF-0007,Hydrogen Plant,Planned Turnaround,2021-01-03,19,21,9.58,0.532,28197,0,1 TA-00000569,REF-0004,CDU,Major Turnaround,2024-05-11,48,54,12.4,0.96,66983,0,0 TA-00000570,REF-0008,Utilities,Major Turnaround,2019-09-27,41,44,6.9,0.881,78261,0,0 TA-00000571,REF-0004,Delayed Coker,Major Turnaround,2028-06-04,15,19,20.19,0.709,23097,0,0 TA-00000572,REF-0002,Hydrocracker,Planned Turnaround,2024-04-15,24,25,2.28,0.737,115078,0,0 TA-00000573,REF-0001,FCCU,Planned Turnaround,2020-08-08,15,17,10.58,0.728,141531,1,0 TA-00000574,REF-0003,Utilities,Pitstop,2021-10-25,9,10,3.92,0.871,113607,0,0 TA-00000575,REF-0003,Flare System,Planned Turnaround,2024-11-11,25,27,7.36,0.969,149570,0,0 TA-00000576,REF-0013,Flare System,Planned Turnaround,2022-02-23,23,28,20.52,0.884,15977,1,0 TA-00000577,REF-0011,Hydrotreating,Planned Turnaround,2028-09-13,19,22,12.3,0.69,34625,0,0 TA-00000578,REF-0007,VDU,Planned Turnaround,2021-09-13,31,36,13.33,0.478,74672,0,0 TA-00000579,REF-0004,Hydrogen Plant,Pitstop,2027-11-05,8,10,16.24,0.798,17532,0,0 TA-00000580,REF-0004,Flare System,Regulatory Outage,2024-10-05,19,22,11.22,0.697,17991,1,0 TA-00000581,REF-0005,VDU,Regulatory Outage,2028-06-04,18,21,14.09,0.687,35010,1,0 TA-00000582,REF-0007,CDU,Planned Turnaround,2021-06-11,29,34,15.32,0.491,65645,1,0 TA-00000583,REF-0002,Sulfur Recovery,Regulatory Outage,2023-08-03,21,24,14.06,0.757,119992,1,0 TA-00000584,REF-0005,Hydrotreating,Pitstop,2028-03-17,13,15,8.66,0.98,72509,1,0 TA-00000585,REF-0009,Utilities,Major Turnaround,2027-10-12,38,43,12.04,0.346,65340,0,1 TA-00000586,REF-0001,Cooling Water,Pitstop,2023-11-29,12,14,13.9,0.584,47820,0,0 TA-00000587,REF-0014,Hydrocracker,Planned Turnaround,2027-02-23,20,22,6.47,0.685,52098,0,0 TA-00000588,REF-0011,Cooling Water,Pitstop,2023-05-09,6,7,5.3,0.978,99811,0,0 TA-00000589,REF-0007,Utilities,Major Turnaround,2019-07-11,28,31,9.64,0.781,112560,0,0 TA-00000590,REF-0002,Alkylation,Major Turnaround,2027-10-20,50,58,15.08,0.715,121639,0,0 TA-00000591,REF-0012,Sulfur Recovery,Planned Turnaround,2024-09-17,29,34,16.79,0.78,51837,0,0 TA-00000592,REF-0004,Tank Farm,Planned Turnaround,2021-08-22,25,27,6.37,0.39,65434,0,0 TA-00000593,REF-0011,FCCU,Pitstop,2023-11-21,6,9,47.63,0.646,117062,0,0 TA-00000594,REF-0011,Flare System,Regulatory Outage,2024-11-06,20,22,7.62,0.863,70307,1,0 TA-00000595,REF-0015,Delayed Coker,Planned Turnaround,2027-06-13,27,32,16.57,0.469,76761,0,0 TA-00000596,REF-0001,Alkylation,Planned Turnaround,2019-05-11,33,42,25.06,0.628,137167,1,0 TA-00000597,REF-0012,Alkylation,Planned Turnaround,2025-01-16,34,36,4.56,0.59,89367,0,0 TA-00000598,REF-0004,Sulfur Recovery,Planned Turnaround,2019-03-02,39,45,13.43,0.356,47722,0,0 TA-00000599,REF-0010,Tank Farm,Major Turnaround,2020-05-18,34,39,12.37,0.385,14442,0,0 TA-00000600,REF-0006,Reformer,Planned Turnaround,2026-09-02,20,24,16.03,0.592,52173,0,0 TA-00000601,REF-0009,Hydrotreating,Planned Turnaround,2025-12-23,29,31,6.54,0.47,40282,0,0 TA-00000602,REF-0013,Flare System,Planned Turnaround,2024-08-31,21,23,7.92,0.518,71550,0,1 TA-00000603,REF-0010,Flare System,Planned Turnaround,2028-01-04,18,21,14.4,0.53,85093,0,0 TA-00000604,REF-0015,Delayed Coker,Planned Turnaround,2021-02-19,17,18,3.8,0.624,93417,0,0 TA-00000605,REF-0007,CDU,Major Turnaround,2025-02-13,48,55,13.37,0.326,112844,0,0 TA-00000606,REF-0009,Hydrotreating,Planned Turnaround,2020-05-25,20,23,10.18,0.577,47711,0,0 TA-00000607,REF-0011,CDU,Planned Turnaround,2025-03-24,28,30,3.58,0.65,76473,1,0 TA-00000608,REF-0010,Reformer,Regulatory Outage,2028-10-11,17,19,10.91,0.798,15838,1,0 TA-00000609,REF-0008,Utilities,Planned Turnaround,2022-04-16,30,36,18.9,0.842,83102,0,0 TA-00000610,REF-0003,Reformer,Major Turnaround,2023-04-01,39,58,47.81,0.649,115997,0,0 TA-00000611,REF-0015,Cooling Water,Pitstop,2024-11-28,9,10,9.67,0.802,166366,0,0 TA-00000612,REF-0015,Hydrotreating,Emergency Shutdown,2022-02-16,6,7,14.41,0.847,77688,0,0 TA-00000613,REF-0006,Sulfur Recovery,Emergency Shutdown,2025-09-16,7,8,10.18,0.699,85079,0,0 TA-00000614,REF-0006,Flare System,Major Turnaround,2024-11-06,54,59,9.1,0.581,16166,0,0 TA-00000615,REF-0001,Cooling Water,Planned Turnaround,2028-12-02,27,29,4.03,0.703,98474,0,0 TA-00000616,REF-0011,Reformer,Regulatory Outage,2023-09-02,12,13,8.06,0.439,44666,1,0 TA-00000617,REF-0013,Hydrocracker,Planned Turnaround,2025-10-26,23,27,16.05,0.941,27047,0,0 TA-00000618,REF-0001,Flare System,Planned Turnaround,2025-02-20,26,29,11.01,0.587,110989,0,0 TA-00000619,REF-0002,Hydrogen Plant,Planned Turnaround,2027-12-29,14,16,13.56,0.561,40759,0,0 TA-00000620,REF-0007,Flare System,Pitstop,2022-11-26,7,9,20.15,0.626,120180,0,0 TA-00000621,REF-0011,VDU,Planned Turnaround,2027-11-24,24,26,6.89,0.457,81975,0,0 TA-00000622,REF-0001,Sulfur Recovery,Planned Turnaround,2024-12-04,27,31,13.14,0.485,102717,0,0 TA-00000623,REF-0015,FCCU,Planned Turnaround,2019-10-22,17,19,9.7,0.575,25862,0,0 TA-00000624,REF-0002,Tank Farm,Planned Turnaround,2022-03-07,40,45,11.27,0.443,90434,0,0 TA-00000625,REF-0011,Utilities,Major Turnaround,2022-03-04,34,40,16.09,0.643,27229,0,0 TA-00000626,REF-0007,Alkylation,Planned Turnaround,2026-10-23,22,23,3.95,0.775,27678,0,0 TA-00000627,REF-0009,Sulfur Recovery,Major Turnaround,2019-10-19,35,39,9.23,0.392,41505,1,0 TA-00000628,REF-0001,Hydrogen Plant,Planned Turnaround,2019-10-01,31,35,12.78,0.52,73579,0,0 TA-00000629,REF-0008,Hydrotreating,Major Turnaround,2025-06-13,42,48,13.58,0.677,12490,0,0 TA-00000630,REF-0013,VDU,Planned Turnaround,2027-11-02,33,46,36.84,0.378,30209,0,0 TA-00000631,REF-0009,CDU,Planned Turnaround,2024-08-05,28,32,13.11,0.79,68088,1,0 TA-00000632,REF-0003,Delayed Coker,Planned Turnaround,2019-05-05,18,19,2.36,0.972,22390,0,0 TA-00000633,REF-0010,FCCU,Planned Turnaround,2025-03-09,17,24,41.06,0.613,15943,0,0 TA-00000634,REF-0001,CDU,Pitstop,2020-11-30,7,8,3.84,0.471,86969,0,0 TA-00000635,REF-0010,VDU,Pitstop,2022-07-06,9,11,13.61,0.406,8558,0,0 TA-00000636,REF-0015,Sulfur Recovery,Emergency Shutdown,2025-07-02,5,6,7.35,0.703,154653,0,0 TA-00000637,REF-0010,Hydrotreating,Major Turnaround,2023-09-06,37,46,22.8,0.65,73715,0,0 TA-00000638,REF-0009,Tank Farm,Pitstop,2022-10-03,11,13,10.49,0.809,82143,0,0 TA-00000639,REF-0015,FCCU,Planned Turnaround,2019-08-16,28,31,10.09,0.864,153814,0,0 TA-00000640,REF-0007,Hydrotreating,Planned Turnaround,2028-02-04,37,44,16.63,0.696,22053,0,0 TA-00000641,REF-0011,Utilities,Planned Turnaround,2023-12-17,41,47,14.21,0.98,71018,0,0 TA-00000642,REF-0001,Tank Farm,Pitstop,2019-03-03,9,11,17.7,0.858,92907,1,0 TA-00000643,REF-0005,Utilities,Planned Turnaround,2027-10-26,26,27,0.65,0.75,89040,0,0 TA-00000644,REF-0012,Reformer,Major Turnaround,2022-01-03,38,42,8.72,0.669,152072,0,0 TA-00000645,REF-0005,Sulfur Recovery,Emergency Shutdown,2024-12-28,5,6,11.85,0.737,54682,0,0 TA-00000646,REF-0002,Delayed Coker,Major Turnaround,2019-06-01,19,23,16.1,0.675,98184,0,0 TA-00000647,REF-0006,Delayed Coker,Pitstop,2019-09-01,10,12,16.03,0.618,26922,0,0 TA-00000648,REF-0007,Reformer,Pitstop,2025-08-15,11,13,11.93,0.664,33812,0,0 TA-00000649,REF-0006,Tank Farm,Pitstop,2021-03-31,8,9,8.06,0.98,34192,0,0 TA-00000650,REF-0011,Flare System,Planned Turnaround,2028-04-23,35,38,5.88,0.601,31851,0,0 TA-00000651,REF-0011,Reformer,Planned Turnaround,2027-11-27,15,17,8.35,0.668,54669,1,0 TA-00000652,REF-0007,Hydrotreating,Planned Turnaround,2022-01-21,23,25,8.5,0.875,85326,0,0 TA-00000653,REF-0008,Cooling Water,Emergency Shutdown,2023-05-10,6,7,11.93,0.809,14590,0,0 TA-00000654,REF-0004,Cooling Water,Major Turnaround,2027-10-09,36,40,8.36,0.81,9702,0,0 TA-00000655,REF-0009,VDU,Planned Turnaround,2023-11-24,22,24,7.39,0.778,42572,0,0 TA-00000656,REF-0008,Tank Farm,Planned Turnaround,2028-07-11,24,27,10.21,0.858,64861,0,0 TA-00000657,REF-0012,VDU,Pitstop,2019-05-14,11,12,8.11,0.63,90926,0,0 TA-00000658,REF-0014,VDU,Regulatory Outage,2026-02-27,22,24,8.67,0.716,9775,1,0 TA-00000659,REF-0006,Tank Farm,Major Turnaround,2022-07-23,43,49,12.29,0.753,30118,0,0 TA-00000660,REF-0006,Hydrocracker,Emergency Shutdown,2022-02-12,3,4,5.43,0.77,17144,0,0 TA-00000661,REF-0012,Hydrogen Plant,Pitstop,2021-05-09,9,10,9.7,0.416,38818,0,1 TA-00000662,REF-0006,Cooling Water,Planned Turnaround,2020-11-07,20,23,10.3,0.658,79195,1,0 TA-00000663,REF-0005,Delayed Coker,Pitstop,2022-04-27,6,7,16.33,0.517,79771,0,0 TA-00000664,REF-0003,Hydrocracker,Planned Turnaround,2028-11-18,38,40,3.97,0.527,15815,0,0 TA-00000665,REF-0003,Reformer,Planned Turnaround,2028-04-25,18,20,9.65,0.547,123716,0,0 TA-00000666,REF-0014,CDU,Major Turnaround,2024-01-11,19,20,2.51,0.578,8665,0,0 TA-00000667,REF-0011,Hydrocracker,Pitstop,2028-08-02,8,9,11.28,0.696,51299,0,0 TA-00000668,REF-0004,Delayed Coker,Planned Turnaround,2020-06-13,12,14,12.18,0.654,79428,1,0 TA-00000669,REF-0012,CDU,Planned Turnaround,2020-12-08,29,33,10.93,0.82,52096,0,0 TA-00000670,REF-0005,Hydrotreating,Pitstop,2025-12-17,11,13,17.96,0.198,28190,0,0 TA-00000671,REF-0014,Alkylation,Planned Turnaround,2022-09-29,18,22,21.59,0.482,21211,0,0 TA-00000672,REF-0003,Delayed Coker,Regulatory Outage,2021-02-25,13,15,7.91,0.809,61523,1,0 TA-00000673,REF-0008,Hydrocracker,Planned Turnaround,2027-04-16,21,25,16.64,0.54,17291,0,0 TA-00000674,REF-0004,Hydrocracker,Planned Turnaround,2022-09-20,26,31,18.25,0.791,37442,0,0 TA-00000675,REF-0002,Reformer,Planned Turnaround,2022-01-15,27,30,8.87,0.332,35873,0,0 TA-00000676,REF-0004,Flare System,Planned Turnaround,2019-11-13,30,34,11.13,0.98,61285,0,0 TA-00000677,REF-0006,Tank Farm,Regulatory Outage,2025-05-25,20,24,16.27,0.463,47464,1,0 TA-00000678,REF-0010,Sulfur Recovery,Pitstop,2019-02-15,10,12,11.73,0.749,85358,0,0 TA-00000679,REF-0013,Flare System,Planned Turnaround,2024-02-10,20,23,13.95,0.767,95027,0,0 TA-00000680,REF-0011,Alkylation,Major Turnaround,2021-10-16,46,53,14.82,0.98,86379,0,1 TA-00000681,REF-0005,Hydrogen Plant,Emergency Shutdown,2019-04-11,8,9,7.12,0.548,91670,0,0 TA-00000682,REF-0010,Sulfur Recovery,Pitstop,2024-09-28,3,4,6.88,0.709,52670,0,0 TA-00000683,REF-0004,Cooling Water,Major Turnaround,2023-01-20,51,58,13.22,0.536,61601,0,0 TA-00000684,REF-0007,FCCU,Planned Turnaround,2027-10-15,25,29,15.52,0.726,54668,0,0 TA-00000685,REF-0005,Alkylation,Planned Turnaround,2020-06-15,31,37,16.5,0.62,15822,0,0 TA-00000686,REF-0002,Hydrotreating,Planned Turnaround,2026-02-28,24,27,9.77,0.578,66591,0,0 TA-00000687,REF-0004,Hydrogen Plant,Planned Turnaround,2026-09-13,24,28,16.65,0.734,37801,0,0 TA-00000688,REF-0013,Sulfur Recovery,Planned Turnaround,2027-03-02,27,32,17.07,0.511,102790,1,0 TA-00000689,REF-0015,VDU,Planned Turnaround,2027-08-10,14,16,12.72,0.316,37197,0,0 TA-00000690,REF-0004,CDU,Major Turnaround,2020-09-23,38,42,10.02,0.564,52427,0,0 TA-00000691,REF-0003,Hydrogen Plant,Planned Turnaround,2020-04-22,40,42,3.79,0.897,128408,0,0 TA-00000692,REF-0004,VDU,Planned Turnaround,2022-10-26,28,30,3.64,0.365,65156,0,0 TA-00000693,REF-0005,CDU,Planned Turnaround,2019-12-29,23,25,7.84,0.745,24614,0,0 TA-00000694,REF-0009,Flare System,Planned Turnaround,2026-12-18,29,33,10.6,0.493,55368,0,0 TA-00000695,REF-0008,Alkylation,Emergency Shutdown,2020-09-29,8,10,13.59,0.536,20404,0,0 TA-00000696,REF-0009,Delayed Coker,Major Turnaround,2020-11-05,44,49,10.42,0.588,35592,1,0 TA-00000697,REF-0003,Tank Farm,Pitstop,2025-04-21,9,10,7.78,0.636,56441,0,0 TA-00000698,REF-0014,Tank Farm,Pitstop,2027-04-28,11,13,10.73,0.45,56014,0,0 TA-00000699,REF-0007,Cooling Water,Pitstop,2023-04-28,9,10,5.81,0.33,98911,0,0 TA-00000700,REF-0009,Delayed Coker,Planned Turnaround,2020-10-22,25,30,17.58,0.663,9187,1,0 TA-00000701,REF-0009,Cooling Water,Regulatory Outage,2019-06-26,21,24,9.94,0.253,60778,1,0 TA-00000702,REF-0006,VDU,Planned Turnaround,2028-08-10,25,29,13.02,0.677,83631,1,0 TA-00000703,REF-0008,FCCU,Major Turnaround,2026-05-22,25,28,10.87,0.883,50936,0,0 TA-00000704,REF-0003,Hydrocracker,Pitstop,2023-04-03,10,12,16.36,0.473,85199,0,0 TA-00000705,REF-0015,Reformer,Planned Turnaround,2023-09-01,30,31,1.99,0.675,81018,0,1 TA-00000706,REF-0015,Hydrotreating,Planned Turnaround,2024-03-04,31,36,13.82,0.637,72819,0,0 TA-00000707,REF-0008,Hydrocracker,Planned Turnaround,2022-07-31,23,25,7.63,0.78,44101,1,0 TA-00000708,REF-0011,Hydrotreating,Planned Turnaround,2020-08-31,15,21,37.66,0.429,106476,0,0 TA-00000709,REF-0014,Cooling Water,Emergency Shutdown,2028-05-07,7,8,14.01,0.651,11183,1,0 TA-00000710,REF-0013,Tank Farm,Major Turnaround,2027-11-30,30,33,9.86,0.645,61249,0,0 TA-00000711,REF-0004,Delayed Coker,Planned Turnaround,2024-11-08,35,42,18.27,0.818,43063,0,0 TA-00000712,REF-0007,Alkylation,Planned Turnaround,2028-11-29,30,34,13.2,0.696,97237,0,0 TA-00000713,REF-0006,CDU,Major Turnaround,2028-09-15,22,25,13.47,0.758,74363,0,0 TA-00000714,REF-0003,Delayed Coker,Planned Turnaround,2019-03-27,12,14,12.08,0.748,31434,1,0 TA-00000715,REF-0013,Hydrogen Plant,Pitstop,2021-10-09,7,8,3.61,0.453,84156,0,0 TA-00000716,REF-0013,Alkylation,Planned Turnaround,2021-09-23,19,22,14.68,0.875,33673,0,0 TA-00000717,REF-0014,Cooling Water,Planned Turnaround,2023-03-21,25,29,13.53,0.749,17572,0,0 TA-00000718,REF-0006,FCCU,Pitstop,2025-05-09,9,10,7.33,0.701,52537,0,0 TA-00000719,REF-0014,VDU,Planned Turnaround,2023-07-30,23,27,13.69,0.78,17614,1,0 TA-00000720,REF-0002,Flare System,Major Turnaround,2028-07-03,39,43,8.22,0.877,112628,0,1 TA-00000721,REF-0001,Sulfur Recovery,Planned Turnaround,2020-02-01,22,24,8.46,0.619,137527,0,0 TA-00000722,REF-0002,Hydrotreating,Pitstop,2028-07-06,9,11,12.6,0.609,15832,0,0 TA-00000723,REF-0003,Hydrocracker,Planned Turnaround,2027-12-29,29,33,10.77,0.492,54665,1,0 TA-00000724,REF-0004,Reformer,Planned Turnaround,2022-12-02,22,27,20.71,0.325,38352,0,0 TA-00000725,REF-0004,Flare System,Planned Turnaround,2019-08-15,33,36,8.09,0.636,40714,0,0 TA-00000726,REF-0013,Utilities,Pitstop,2020-08-12,9,10,9.17,0.529,57553,0,0 TA-00000727,REF-0011,Hydrocracker,Planned Turnaround,2023-04-05,11,12,8.02,0.366,79350,0,0 TA-00000728,REF-0015,FCCU,Planned Turnaround,2028-11-05,31,38,20.51,0.423,140704,1,0 TA-00000729,REF-0011,FCCU,Planned Turnaround,2025-06-17,32,38,16.3,0.454,132462,1,0 TA-00000730,REF-0004,FCCU,Planned Turnaround,2021-01-12,24,28,15.15,0.924,41299,1,0 TA-00000731,REF-0002,Hydrogen Plant,Planned Turnaround,2025-08-27,18,21,15.53,0.833,80271,0,0 TA-00000732,REF-0015,Flare System,Planned Turnaround,2026-07-30,24,25,3.27,0.628,51445,0,0 TA-00000733,REF-0004,Utilities,Planned Turnaround,2026-03-23,28,33,16.53,0.552,19721,0,0 TA-00000734,REF-0007,Hydrogen Plant,Pitstop,2028-01-29,4,5,13.38,0.212,113991,0,0 TA-00000735,REF-0009,CDU,Emergency Shutdown,2026-12-28,3,4,14.16,0.581,59596,0,0 TA-00000736,REF-0009,Tank Farm,Pitstop,2028-10-01,6,8,20.64,0.337,74879,0,0 TA-00000737,REF-0011,Cooling Water,Planned Turnaround,2027-10-18,33,40,19.76,0.416,106663,0,0 TA-00000738,REF-0015,Flare System,Pitstop,2019-05-07,10,11,6.27,0.729,88037,0,0 TA-00000739,REF-0002,Hydrocracker,Planned Turnaround,2025-06-04,27,30,10.79,0.645,27321,1,0 TA-00000740,REF-0001,Hydrotreating,Planned Turnaround,2028-07-23,19,22,11.3,0.477,97950,1,0 TA-00000741,REF-0014,FCCU,Planned Turnaround,2021-03-28,32,36,12.43,0.676,17830,0,0 TA-00000742,REF-0006,CDU,Planned Turnaround,2023-11-22,27,30,9.3,0.682,56984,0,0 TA-00000743,REF-0010,Tank Farm,Planned Turnaround,2028-10-21,15,17,13.02,0.797,84674,0,0 TA-00000744,REF-0002,Hydrotreating,Major Turnaround,2028-02-03,20,23,12.77,0.817,38158,1,0 TA-00000745,REF-0009,CDU,Major Turnaround,2021-01-10,34,37,7.34,0.691,17927,0,0 TA-00000746,REF-0013,Utilities,Major Turnaround,2021-05-09,34,46,33.88,0.695,103994,0,0 TA-00000747,REF-0001,Hydrocracker,Planned Turnaround,2020-08-03,25,28,10.65,0.873,33591,0,1 TA-00000748,REF-0013,Flare System,Planned Turnaround,2023-10-26,36,45,24.63,0.442,42678,0,1 TA-00000749,REF-0003,Delayed Coker,Major Turnaround,2025-09-19,30,33,7.31,0.607,84791,0,0 TA-00000750,REF-0007,Hydrocracker,Planned Turnaround,2027-10-16,27,33,18.65,0.98,16884,1,0 TA-00000751,REF-0002,VDU,Major Turnaround,2028-07-25,46,57,22.26,0.706,74126,0,0 TA-00000752,REF-0001,Cooling Water,Planned Turnaround,2021-10-19,24,29,18.99,0.722,158616,0,0 TA-00000753,REF-0004,Hydrocracker,Planned Turnaround,2021-12-13,15,18,14.1,0.619,63012,0,0 TA-00000754,REF-0002,Delayed Coker,Planned Turnaround,2021-10-03,10,11,7.83,0.48,94429,0,0 TA-00000755,REF-0004,Sulfur Recovery,Planned Turnaround,2021-12-16,34,41,20.07,0.614,73007,0,0 TA-00000756,REF-0008,Reformer,Planned Turnaround,2028-06-29,33,39,17.64,0.49,53760,0,0 TA-00000757,REF-0005,CDU,Planned Turnaround,2026-03-22,25,29,13.88,0.793,21068,0,0 TA-00000758,REF-0005,Hydrogen Plant,Regulatory Outage,2019-11-21,24,28,13.76,0.549,108669,1,0 TA-00000759,REF-0014,Hydrogen Plant,Pitstop,2020-02-14,8,9,8.28,0.524,47249,0,1 TA-00000760,REF-0002,Utilities,Pitstop,2028-08-11,13,16,15.69,0.515,38466,0,0 TA-00000761,REF-0007,Cooling Water,Planned Turnaround,2027-04-08,34,39,12.28,0.382,75418,0,0 TA-00000762,REF-0004,Delayed Coker,Major Turnaround,2021-03-04,47,52,9.68,0.528,22001,1,0 TA-00000763,REF-0005,Alkylation,Pitstop,2020-04-10,8,10,13.47,0.781,34390,0,0 TA-00000764,REF-0006,Utilities,Planned Turnaround,2026-11-10,28,33,15.82,0.465,86346,0,0 TA-00000765,REF-0007,Hydrocracker,Planned Turnaround,2019-01-06,39,45,13.7,0.41,30199,0,0 TA-00000766,REF-0011,Delayed Coker,Major Turnaround,2022-01-09,35,42,18.99,0.41,122261,1,1 TA-00000767,REF-0007,Reformer,Pitstop,2019-09-30,10,12,10.3,0.727,88958,0,0 TA-00000768,REF-0003,Cooling Water,Planned Turnaround,2028-10-24,27,28,2.58,0.7,48613,1,0 TA-00000769,REF-0011,FCCU,Emergency Shutdown,2019-01-02,9,11,12.61,0.889,110668,0,0 TA-00000770,REF-0011,Hydrotreating,Planned Turnaround,2027-01-08,28,33,15.12,0.684,40024,0,0 TA-00000771,REF-0002,VDU,Planned Turnaround,2026-11-25,29,34,14.47,0.418,51721,0,0 TA-00000772,REF-0001,CDU,Planned Turnaround,2027-10-28,30,34,10.5,0.564,157708,0,0 TA-00000773,REF-0006,CDU,Major Turnaround,2027-08-03,32,36,10.07,0.648,56609,1,0 TA-00000774,REF-0010,Sulfur Recovery,Planned Turnaround,2022-05-22,21,23,8.42,0.309,84280,0,0 TA-00000775,REF-0004,Hydrocracker,Major Turnaround,2027-05-28,31,34,9.53,0.345,27227,1,0 TA-00000776,REF-0001,Hydrotreating,Regulatory Outage,2019-01-31,17,19,10.23,0.401,55179,1,0 TA-00000777,REF-0009,Hydrotreating,Planned Turnaround,2023-01-16,35,40,12.9,0.54,77041,0,0 TA-00000778,REF-0013,CDU,Regulatory Outage,2026-06-04,17,19,10.21,0.815,51636,1,0 TA-00000779,REF-0004,Sulfur Recovery,Planned Turnaround,2019-07-02,31,34,6.87,0.66,44051,0,0 TA-00000780,REF-0013,Hydrocracker,Planned Turnaround,2022-04-19,28,31,7.5,0.567,42313,1,0 TA-00000781,REF-0002,Flare System,Major Turnaround,2028-05-21,46,53,14.25,0.436,65566,0,0 TA-00000782,REF-0014,Hydrogen Plant,Planned Turnaround,2022-02-20,10,11,5.97,0.544,37343,0,0 TA-00000783,REF-0012,CDU,Major Turnaround,2027-10-03,34,40,15.33,0.452,93352,0,0 TA-00000784,REF-0006,Delayed Coker,Planned Turnaround,2021-01-27,16,17,4.57,0.444,84921,0,0 TA-00000785,REF-0001,Utilities,Emergency Shutdown,2026-03-15,8,9,7.37,0.709,67723,0,0 TA-00000786,REF-0014,Delayed Coker,Major Turnaround,2026-05-25,57,67,16.68,0.606,17825,0,0 TA-00000787,REF-0015,VDU,Planned Turnaround,2021-10-24,30,36,16.82,0.443,36418,0,0 TA-00000788,REF-0007,Hydrocracker,Major Turnaround,2025-10-15,49,54,8.17,0.675,47475,0,0 TA-00000789,REF-0007,Hydrotreating,Planned Turnaround,2028-07-11,23,26,11.09,0.784,50132,0,0 TA-00000790,REF-0002,FCCU,Major Turnaround,2021-03-14,47,51,7.04,0.592,62520,0,0 TA-00000791,REF-0010,Flare System,Planned Turnaround,2025-05-04,26,30,12.3,0.639,46359,0,0 TA-00000792,REF-0001,Utilities,Pitstop,2028-07-15,14,15,4.12,0.731,31643,0,0 TA-00000793,REF-0006,VDU,Planned Turnaround,2020-12-13,22,23,2.8,0.599,63792,0,0 TA-00000794,REF-0015,Utilities,Emergency Shutdown,2025-05-27,7,8,13.54,0.636,23101,0,1 TA-00000795,REF-0001,Cooling Water,Major Turnaround,2027-10-21,33,37,9.2,0.521,147006,0,0 TA-00000796,REF-0007,Hydrocracker,Planned Turnaround,2021-05-30,25,30,19.83,0.737,46721,1,0 TA-00000797,REF-0005,Flare System,Major Turnaround,2025-05-31,44,54,22.6,0.733,91691,1,0 TA-00000798,REF-0004,Hydrotreating,Planned Turnaround,2028-09-06,23,27,13.5,0.438,55205,0,0 TA-00000799,REF-0002,Sulfur Recovery,Emergency Shutdown,2023-12-04,6,7,12.02,0.263,37938,0,0 TA-00000800,REF-0014,Tank Farm,Pitstop,2024-03-22,12,14,11.32,0.525,44536,0,0 TA-00000801,REF-0013,Cooling Water,Planned Turnaround,2025-02-27,29,32,8.14,0.327,46987,0,0 TA-00000802,REF-0007,Utilities,Major Turnaround,2019-01-09,43,49,13.87,0.76,78620,0,0 TA-00000803,REF-0001,Delayed Coker,Planned Turnaround,2023-09-10,26,30,13.83,0.564,42119,0,0 TA-00000804,REF-0011,Tank Farm,Major Turnaround,2020-02-20,54,63,16.1,0.613,13995,0,0 TA-00000805,REF-0001,CDU,Planned Turnaround,2025-12-08,23,24,1.42,0.525,108545,0,0 TA-00000806,REF-0005,Tank Farm,Planned Turnaround,2021-02-03,30,36,17.72,0.931,62311,0,1 TA-00000807,REF-0002,Utilities,Major Turnaround,2022-02-13,22,25,9.9,0.64,68054,0,0 TA-00000808,REF-0015,Sulfur Recovery,Planned Turnaround,2019-12-13,30,35,16.67,0.971,74641,0,0 TA-00000809,REF-0009,Cooling Water,Major Turnaround,2026-10-15,44,69,55.57,0.497,73545,0,0 TA-00000810,REF-0015,CDU,Planned Turnaround,2020-12-23,20,23,13.1,0.782,93607,1,0 TA-00000811,REF-0003,Sulfur Recovery,Planned Turnaround,2022-11-26,27,30,8.16,0.585,137076,0,0 TA-00000812,REF-0012,Sulfur Recovery,Planned Turnaround,2026-04-05,20,24,16.48,0.249,107939,1,0 TA-00000813,REF-0014,Utilities,Pitstop,2027-08-29,13,15,15.35,0.584,36060,0,1 TA-00000814,REF-0008,VDU,Planned Turnaround,2020-08-23,26,29,11.3,0.403,22802,0,0 TA-00000815,REF-0003,Hydrocracker,Planned Turnaround,2021-11-29,24,25,3.71,0.45,75806,0,0 TA-00000816,REF-0014,Reformer,Planned Turnaround,2028-11-30,18,21,11.34,0.597,16952,0,0 TA-00000817,REF-0003,Hydrotreating,Major Turnaround,2022-01-25,46,50,6.92,0.768,68343,0,0 TA-00000818,REF-0015,Hydrogen Plant,Planned Turnaround,2023-01-07,18,20,10.78,0.524,142598,0,0 TA-00000819,REF-0013,Reformer,Planned Turnaround,2022-04-24,23,27,13.95,0.539,44081,0,0 TA-00000820,REF-0006,Hydrogen Plant,Major Turnaround,2027-07-17,40,50,22.96,0.616,50771,0,0 TA-00000821,REF-0002,VDU,Major Turnaround,2026-05-15,48,70,44.88,0.599,33553,0,0 TA-00000822,REF-0004,Reformer,Planned Turnaround,2024-01-26,25,30,19.86,0.542,12757,0,0 TA-00000823,REF-0001,VDU,Planned Turnaround,2028-09-27,26,30,15.26,0.683,86720,0,0 TA-00000824,REF-0005,Reformer,Major Turnaround,2024-08-06,47,50,5.95,0.905,104703,0,0 TA-00000825,REF-0009,Cooling Water,Pitstop,2020-02-05,11,13,12.08,0.404,27590,1,1 TA-00000826,REF-0015,Hydrocracker,Planned Turnaround,2022-11-06,27,31,12.86,0.404,74116,0,0 TA-00000827,REF-0011,Delayed Coker,Planned Turnaround,2025-10-21,21,23,4.94,0.737,118508,0,0 TA-00000828,REF-0007,Tank Farm,Emergency Shutdown,2024-02-13,8,9,9.21,0.758,143834,0,0 TA-00000829,REF-0008,Cooling Water,Planned Turnaround,2021-12-06,26,29,10.48,0.913,59276,0,0 TA-00000830,REF-0001,Hydrogen Plant,Planned Turnaround,2026-02-25,26,33,25.59,0.97,74094,0,0 TA-00000831,REF-0011,Tank Farm,Emergency Shutdown,2024-03-08,9,11,15.82,0.581,131076,0,0 TA-00000832,REF-0008,Reformer,Planned Turnaround,2022-09-04,29,35,17.79,0.322,78587,0,0 TA-00000833,REF-0011,Reformer,Emergency Shutdown,2023-10-31,6,7,9.88,0.5,74971,0,0 TA-00000834,REF-0003,Tank Farm,Planned Turnaround,2022-01-21,32,37,12.99,0.81,127431,0,0 TA-00000835,REF-0013,Sulfur Recovery,Planned Turnaround,2023-09-12,28,30,4.96,0.695,97473,0,1 TA-00000836,REF-0006,Hydrotreating,Planned Turnaround,2019-02-23,25,27,7.92,0.742,76740,0,0 TA-00000837,REF-0003,Hydrogen Plant,Planned Turnaround,2024-07-31,16,19,14.29,0.427,75600,1,0 TA-00000838,REF-0010,Tank Farm,Planned Turnaround,2021-12-18,32,37,14.78,0.491,45378,0,0 TA-00000839,REF-0012,Hydrogen Plant,Pitstop,2025-10-13,12,14,8.34,0.738,63909,0,0 TA-00000840,REF-0005,FCCU,Regulatory Outage,2028-08-19,13,16,17.34,0.359,17974,1,0 TA-00000841,REF-0009,Tank Farm,Planned Turnaround,2020-12-30,22,24,6.41,0.535,45902,0,0 TA-00000842,REF-0014,Delayed Coker,Planned Turnaround,2020-08-18,17,20,16.75,0.913,13641,0,0 TA-00000843,REF-0008,Alkylation,Major Turnaround,2024-07-11,46,54,15.51,0.569,34927,0,0 TA-00000844,REF-0014,Tank Farm,Planned Turnaround,2027-11-21,28,31,8.77,0.667,16550,0,0 TA-00000845,REF-0002,Sulfur Recovery,Planned Turnaround,2024-03-07,21,25,14.86,0.702,17657,0,0 TA-00000846,REF-0008,Hydrotreating,Planned Turnaround,2028-01-02,34,39,14.7,0.47,7724,1,0 TA-00000847,REF-0004,Reformer,Major Turnaround,2024-09-13,48,53,9.81,0.486,70516,0,0 TA-00000848,REF-0007,Utilities,Pitstop,2019-05-11,6,7,7.23,0.381,135035,0,1 TA-00000849,REF-0006,Reformer,Planned Turnaround,2023-01-21,33,36,8.65,0.506,10720,0,1 TA-00000850,REF-0001,Reformer,Major Turnaround,2024-03-03,42,48,13.78,0.654,30319,1,0 TA-00000851,REF-0014,Sulfur Recovery,Pitstop,2025-10-01,14,16,13.22,0.495,14911,0,0 TA-00000852,REF-0015,Hydrotreating,Planned Turnaround,2020-05-08,20,23,10.97,0.61,148667,0,0 TA-00000853,REF-0012,Flare System,Planned Turnaround,2027-10-14,26,27,3.73,0.526,132156,0,0 TA-00000854,REF-0015,Cooling Water,Planned Turnaround,2027-11-01,28,30,7.07,0.878,40882,0,0 TA-00000855,REF-0011,VDU,Pitstop,2021-10-07,13,16,15.66,0.268,47705,0,0 TA-00000856,REF-0004,Sulfur Recovery,Planned Turnaround,2028-02-27,15,18,15.12,0.754,15101,0,0 TA-00000857,REF-0009,Sulfur Recovery,Planned Turnaround,2019-08-30,35,38,7.43,0.449,62238,0,0 TA-00000858,REF-0001,Reformer,Pitstop,2026-01-30,3,4,22.78,0.674,105615,0,0 TA-00000859,REF-0005,Hydrotreating,Pitstop,2020-04-11,10,12,18.08,0.579,30145,0,0 TA-00000860,REF-0014,Hydrocracker,Planned Turnaround,2023-05-27,26,30,14.35,0.57,13547,0,0 TA-00000861,REF-0010,Alkylation,Planned Turnaround,2028-07-29,18,21,16.0,0.354,14848,1,0 TA-00000862,REF-0014,Cooling Water,Major Turnaround,2024-11-18,40,44,9.42,0.426,25488,0,0 TA-00000863,REF-0009,Flare System,Planned Turnaround,2027-05-27,22,24,6.95,0.599,65194,0,0 TA-00000864,REF-0007,Hydrotreating,Planned Turnaround,2025-02-07,20,22,8.74,0.378,106394,0,0 TA-00000865,REF-0010,Alkylation,Pitstop,2028-06-19,3,4,13.26,0.762,16130,0,0 TA-00000866,REF-0012,Hydrocracker,Planned Turnaround,2024-01-30,28,32,11.86,0.613,115673,0,0 TA-00000867,REF-0008,Delayed Coker,Major Turnaround,2022-07-05,67,74,10.11,0.75,43888,0,0 TA-00000868,REF-0001,Reformer,Pitstop,2026-04-24,9,10,7.55,0.656,150563,0,0 TA-00000869,REF-0013,Utilities,Planned Turnaround,2019-03-03,26,29,9.22,0.569,49566,0,0 TA-00000870,REF-0015,Hydrocracker,Planned Turnaround,2020-09-25,24,27,11.51,0.434,135239,0,0 TA-00000871,REF-0014,FCCU,Planned Turnaround,2028-03-13,38,42,9.63,0.165,16962,0,0 TA-00000872,REF-0006,Hydrogen Plant,Planned Turnaround,2022-09-22,26,30,13.6,0.568,40677,0,0 TA-00000873,REF-0003,Cooling Water,Planned Turnaround,2022-03-24,19,22,15.59,0.238,87118,0,0 TA-00000874,REF-0007,Hydrotreating,Pitstop,2020-08-26,7,8,9.45,0.31,67795,0,0 TA-00000875,REF-0007,CDU,Planned Turnaround,2022-01-12,21,24,13.9,0.865,54241,0,0 TA-00000876,REF-0007,FCCU,Pitstop,2027-12-11,10,11,5.09,0.686,36712,0,0 TA-00000877,REF-0003,Flare System,Planned Turnaround,2028-07-09,27,30,10.04,0.673,155354,0,0 TA-00000878,REF-0004,Reformer,Major Turnaround,2019-04-06,53,60,12.04,0.291,34518,0,0 TA-00000879,REF-0004,Flare System,Planned Turnaround,2028-08-22,19,21,7.97,0.384,72429,0,0 TA-00000880,REF-0003,Utilities,Major Turnaround,2027-06-30,45,53,15.59,0.569,99771,0,0 TA-00000881,REF-0005,Cooling Water,Pitstop,2019-02-19,13,15,12.44,0.437,97327,0,0 TA-00000882,REF-0001,Hydrocracker,Planned Turnaround,2021-11-02,29,33,11.85,0.441,22112,0,0 TA-00000883,REF-0010,Sulfur Recovery,Planned Turnaround,2019-09-22,22,26,13.68,0.796,69969,0,0 TA-00000884,REF-0009,Alkylation,Regulatory Outage,2024-06-14,25,29,15.82,0.562,66231,1,0 TA-00000885,REF-0003,FCCU,Regulatory Outage,2024-10-26,17,20,14.56,0.472,106239,1,0 TA-00000886,REF-0006,Alkylation,Planned Turnaround,2019-10-18,31,35,11.45,0.624,12615,0,0 TA-00000887,REF-0014,Tank Farm,Regulatory Outage,2022-11-27,11,13,9.86,0.622,52419,1,0 TA-00000888,REF-0005,Hydrotreating,Planned Turnaround,2023-10-13,34,35,1.51,0.715,81466,1,0 TA-00000889,REF-0008,Delayed Coker,Planned Turnaround,2026-03-25,24,27,11.71,0.699,25747,0,0 TA-00000890,REF-0014,FCCU,Planned Turnaround,2028-08-22,34,38,9.57,0.643,24476,0,0 TA-00000891,REF-0009,Alkylation,Emergency Shutdown,2026-11-08,9,11,14.33,0.72,76321,1,0 TA-00000892,REF-0003,Alkylation,Planned Turnaround,2019-08-10,31,35,12.69,0.343,64884,0,0 TA-00000893,REF-0003,CDU,Planned Turnaround,2027-04-19,26,28,6.69,0.711,65756,0,0 TA-00000894,REF-0002,Reformer,Planned Turnaround,2028-02-24,25,28,10.92,0.531,83800,0,0 TA-00000895,REF-0015,Hydrogen Plant,Emergency Shutdown,2022-06-27,7,8,13.6,0.474,129646,0,0 TA-00000896,REF-0014,Cooling Water,Pitstop,2027-05-28,9,11,17.51,0.749,7501,0,0 TA-00000897,REF-0002,Delayed Coker,Planned Turnaround,2026-04-15,27,31,13.66,0.394,40430,0,1 TA-00000898,REF-0013,Alkylation,Planned Turnaround,2021-05-18,28,31,7.57,0.575,22411,1,0 TA-00000899,REF-0014,Cooling Water,Planned Turnaround,2024-03-15,30,34,10.12,0.519,12255,0,0 TA-00000900,REF-0008,Reformer,Major Turnaround,2026-11-23,54,57,4.14,0.724,24155,0,0 TA-00000901,REF-0014,Flare System,Planned Turnaround,2026-02-28,23,25,6.16,0.705,42530,0,0 TA-00000902,REF-0010,Alkylation,Pitstop,2025-07-11,9,10,7.66,0.5,83486,0,0 TA-00000903,REF-0008,Hydrogen Plant,Planned Turnaround,2020-01-26,27,29,6.31,0.631,81643,0,0 TA-00000904,REF-0004,Hydrotreating,Planned Turnaround,2024-06-12,13,16,17.5,0.731,19121,0,0 TA-00000905,REF-0015,FCCU,Planned Turnaround,2019-08-07,18,21,13.27,0.732,103500,1,0 TA-00000906,REF-0008,Flare System,Pitstop,2019-04-21,8,10,13.12,0.609,61734,0,0 TA-00000907,REF-0015,Cooling Water,Planned Turnaround,2020-03-11,35,40,12.18,0.98,109237,0,0 TA-00000908,REF-0010,Hydrotreating,Regulatory Outage,2025-12-29,16,17,5.4,0.674,81206,1,0 TA-00000909,REF-0015,Hydrocracker,Emergency Shutdown,2026-07-29,7,11,54.8,0.382,166102,0,0 TA-00000910,REF-0008,Utilities,Pitstop,2021-12-07,12,14,10.78,0.898,23505,0,0 TA-00000911,REF-0008,Tank Farm,Major Turnaround,2023-03-22,59,68,13.67,0.423,31814,0,0 TA-00000912,REF-0010,Reformer,Planned Turnaround,2026-04-23,29,41,38.28,0.787,88363,0,0 TA-00000913,REF-0006,Cooling Water,Planned Turnaround,2025-09-15,12,14,15.06,0.782,54532,1,0 TA-00000914,REF-0007,Delayed Coker,Planned Turnaround,2019-11-02,25,27,7.45,0.34,67036,0,0 TA-00000915,REF-0015,Delayed Coker,Planned Turnaround,2019-04-22,30,35,16.43,0.435,149118,0,0 TA-00000916,REF-0008,Hydrogen Plant,Planned Turnaround,2021-02-20,22,25,10.75,0.456,65805,0,0 TA-00000917,REF-0007,FCCU,Pitstop,2027-11-06,12,13,3.99,0.612,93283,0,0 TA-00000918,REF-0010,FCCU,Planned Turnaround,2021-10-30,24,28,14.28,0.792,34636,0,0 TA-00000919,REF-0006,Reformer,Regulatory Outage,2026-03-05,20,23,12.11,0.685,72812,1,0 TA-00000920,REF-0001,Utilities,Planned Turnaround,2025-01-12,37,54,44.74,0.635,165959,0,0 TA-00000921,REF-0013,Tank Farm,Major Turnaround,2019-01-31,37,40,7.59,0.486,55681,0,0 TA-00000922,REF-0010,Tank Farm,Major Turnaround,2019-01-31,49,56,13.16,0.52,57635,0,0 TA-00000923,REF-0007,Tank Farm,Major Turnaround,2019-11-26,48,53,9.63,0.798,34862,0,0 TA-00000924,REF-0011,Flare System,Planned Turnaround,2026-01-28,22,25,11.4,0.326,52382,0,0 TA-00000925,REF-0013,Hydrotreating,Major Turnaround,2023-02-22,30,34,11.17,0.919,64604,0,0 TA-00000926,REF-0005,Reformer,Planned Turnaround,2020-02-23,25,29,13.81,0.535,31246,0,0 TA-00000927,REF-0009,Utilities,Pitstop,2026-01-08,11,12,6.06,0.683,12807,0,0 TA-00000928,REF-0014,Hydrocracker,Planned Turnaround,2021-03-19,29,32,9.82,0.702,15522,0,1 TA-00000929,REF-0010,Flare System,Planned Turnaround,2021-08-18,19,21,9.45,0.753,41116,0,0 TA-00000930,REF-0010,Delayed Coker,Planned Turnaround,2022-06-09,17,20,17.61,0.672,51008,0,0 TA-00000931,REF-0006,VDU,Planned Turnaround,2019-10-29,32,35,8.18,0.698,50424,0,0 TA-00000932,REF-0006,Hydrotreating,Planned Turnaround,2026-11-03,23,26,12.67,0.756,33388,0,0 TA-00000933,REF-0012,VDU,Planned Turnaround,2023-01-01,23,27,13.13,0.478,66221,1,0 TA-00000934,REF-0012,CDU,Planned Turnaround,2028-10-14,27,29,6.99,0.675,45103,0,0 TA-00000935,REF-0007,Alkylation,Planned Turnaround,2025-08-07,38,43,12.91,0.465,13881,0,1 TA-00000936,REF-0014,Delayed Coker,Major Turnaround,2024-10-03,54,62,14.51,0.407,6351,0,0 TA-00000937,REF-0006,Hydrocracker,Planned Turnaround,2022-06-10,31,35,11.73,0.356,20869,0,1 TA-00000938,REF-0004,Reformer,Planned Turnaround,2028-05-28,22,23,4.12,0.757,51571,0,0 TA-00000939,REF-0002,VDU,Emergency Shutdown,2019-06-14,7,8,11.92,0.952,17063,0,0 TA-00000940,REF-0015,Hydrocracker,Planned Turnaround,2021-11-03,32,34,4.33,0.498,15919,0,0 TA-00000941,REF-0012,Hydrogen Plant,Emergency Shutdown,2024-03-02,8,10,12.52,0.796,55983,1,0 TA-00000942,REF-0011,Delayed Coker,Planned Turnaround,2024-06-29,25,29,13.17,0.454,132564,1,0 TA-00000943,REF-0014,VDU,Major Turnaround,2027-07-26,48,51,5.96,0.504,19329,0,0 TA-00000944,REF-0011,Tank Farm,Regulatory Outage,2021-11-09,13,15,8.56,0.695,87510,1,0 TA-00000945,REF-0009,Sulfur Recovery,Planned Turnaround,2022-07-31,26,29,8.93,0.794,53921,0,0 TA-00000946,REF-0014,FCCU,Planned Turnaround,2027-05-13,35,36,2.63,0.604,55413,0,0 TA-00000947,REF-0013,Alkylation,Planned Turnaround,2020-03-18,21,22,4.64,0.528,32073,0,0 TA-00000948,REF-0001,Reformer,Pitstop,2024-04-02,11,13,16.16,0.439,168276,0,0 TA-00000949,REF-0004,Cooling Water,Planned Turnaround,2021-08-22,33,36,6.94,0.709,34560,0,0 TA-00000950,REF-0010,Cooling Water,Pitstop,2021-08-06,10,12,16.39,0.723,40683,0,0 TA-00000951,REF-0003,Hydrotreating,Pitstop,2022-01-29,13,15,14.36,0.581,53053,0,0 TA-00000952,REF-0001,FCCU,Pitstop,2022-05-11,10,12,17.13,0.663,163949,0,0 TA-00000953,REF-0012,Flare System,Planned Turnaround,2023-02-11,19,22,10.58,0.29,108701,0,0 TA-00000954,REF-0014,Hydrogen Plant,Planned Turnaround,2023-10-05,20,23,10.84,0.308,36299,0,0 TA-00000955,REF-0004,Sulfur Recovery,Emergency Shutdown,2020-02-19,6,7,12.84,0.645,53113,0,0 TA-00000956,REF-0012,Tank Farm,Planned Turnaround,2026-08-13,22,25,9.82,0.472,110427,0,0 TA-00000957,REF-0011,Sulfur Recovery,Planned Turnaround,2028-04-13,38,43,13.01,0.456,106033,0,0 TA-00000958,REF-0009,FCCU,Planned Turnaround,2025-09-20,29,33,10.82,0.557,81365,0,0 TA-00000959,REF-0001,Utilities,Major Turnaround,2020-11-29,55,60,8.53,0.625,55805,0,0 TA-00000960,REF-0006,Hydrotreating,Planned Turnaround,2023-08-11,41,47,13.27,0.731,49010,0,0 TA-00000961,REF-0002,Hydrogen Plant,Planned Turnaround,2026-07-18,26,39,48.42,0.767,39704,0,0 TA-00000962,REF-0011,Hydrogen Plant,Planned Turnaround,2020-12-09,35,38,7.23,0.782,42600,0,0 TA-00000963,REF-0005,VDU,Planned Turnaround,2023-08-01,16,19,16.72,0.5,56931,0,1 TA-00000964,REF-0002,Tank Farm,Planned Turnaround,2019-05-31,29,31,5.86,0.719,12369,0,0 TA-00000965,REF-0008,Hydrogen Plant,Planned Turnaround,2023-03-24,25,27,7.75,0.451,24620,0,0 TA-00000966,REF-0010,Sulfur Recovery,Emergency Shutdown,2023-05-14,8,9,8.25,0.471,70667,0,0 TA-00000967,REF-0015,Tank Farm,Pitstop,2021-04-23,14,16,12.4,0.508,155215,0,0 TA-00000968,REF-0001,Cooling Water,Planned Turnaround,2021-02-23,23,26,9.31,0.554,48018,0,0 TA-00000969,REF-0005,Hydrogen Plant,Planned Turnaround,2019-07-15,24,26,7.03,0.744,89616,1,0 TA-00000970,REF-0011,Reformer,Pitstop,2028-08-29,8,10,16.92,0.938,46863,0,0 TA-00000971,REF-0011,Hydrogen Plant,Planned Turnaround,2021-03-18,26,29,10.7,0.489,112587,0,0 TA-00000972,REF-0005,Utilities,Planned Turnaround,2025-11-20,26,29,11.53,0.98,51471,0,0 TA-00000973,REF-0001,Hydrocracker,Planned Turnaround,2024-06-18,21,22,1.46,0.259,145338,0,0 TA-00000974,REF-0015,Tank Farm,Planned Turnaround,2020-01-22,13,15,10.93,0.683,65906,0,0 TA-00000975,REF-0009,Cooling Water,Major Turnaround,2028-07-12,50,57,12.95,0.613,50026,1,0 TA-00000976,REF-0006,FCCU,Planned Turnaround,2027-05-05,28,29,1.95,0.525,34724,0,1 TA-00000977,REF-0008,Hydrogen Plant,Regulatory Outage,2020-01-10,16,18,7.88,0.567,25500,1,0 TA-00000978,REF-0005,Cooling Water,Planned Turnaround,2027-09-07,28,32,12.16,0.593,102961,0,0 TA-00000979,REF-0006,VDU,Planned Turnaround,2019-08-27,34,40,16.68,0.98,30535,0,0 TA-00000980,REF-0003,Delayed Coker,Planned Turnaround,2022-05-10,21,24,13.05,0.628,115041,1,0 TA-00000981,REF-0008,Hydrotreating,Pitstop,2027-01-06,8,10,19.15,0.501,14247,0,1 TA-00000982,REF-0012,Reformer,Planned Turnaround,2026-06-07,23,25,5.91,0.753,112659,0,0 TA-00000983,REF-0010,Hydrotreating,Planned Turnaround,2019-07-21,35,38,6.89,0.536,74194,0,0 TA-00000984,REF-0004,Hydrotreating,Major Turnaround,2024-11-23,41,45,9.02,0.491,71204,0,1 TA-00000985,REF-0013,Delayed Coker,Pitstop,2026-05-31,9,10,9.93,0.98,49100,0,0 TA-00000986,REF-0006,Hydrotreating,Regulatory Outage,2020-11-27,13,15,10.73,0.818,95588,1,0 TA-00000987,REF-0002,Utilities,Planned Turnaround,2028-11-14,33,38,12.65,0.781,34462,0,0 TA-00000988,REF-0009,Hydrogen Plant,Emergency Shutdown,2023-12-29,7,8,7.63,0.459,51474,0,0 TA-00000989,REF-0001,Alkylation,Planned Turnaround,2027-03-10,20,23,13.92,0.933,19662,1,0 TA-00000990,REF-0013,Hydrocracker,Emergency Shutdown,2028-06-08,6,7,7.78,0.749,60409,0,0 TA-00000991,REF-0012,Tank Farm,Planned Turnaround,2026-12-20,18,21,11.35,0.545,116209,0,0 TA-00000992,REF-0001,Tank Farm,Planned Turnaround,2025-09-25,40,47,17.49,0.921,155136,0,0 TA-00000993,REF-0008,Delayed Coker,Planned Turnaround,2026-12-06,29,31,3.54,0.777,11257,0,0 TA-00000994,REF-0015,FCCU,Planned Turnaround,2027-08-21,41,46,10.58,0.682,80059,0,0 TA-00000995,REF-0007,Delayed Coker,Planned Turnaround,2028-09-24,23,25,6.73,0.15,98878,0,0 TA-00000996,REF-0008,CDU,Planned Turnaround,2022-08-07,35,39,9.98,0.64,15413,0,0 TA-00000997,REF-0012,Sulfur Recovery,Pitstop,2020-04-02,11,13,11.35,0.625,74474,0,0 TA-00000998,REF-0006,Hydrotreating,Planned Turnaround,2027-12-11,31,37,18.27,0.539,19548,0,0 TA-00000999,REF-0015,FCCU,Regulatory Outage,2019-05-25,25,29,13.9,0.637,133544,1,0 TA-00001000,REF-0005,Flare System,Planned Turnaround,2021-01-03,24,25,3.73,0.506,18974,0,0 TA-00001001,REF-0009,VDU,Planned Turnaround,2025-05-14,26,29,11.15,0.6,80220,0,0 TA-00001002,REF-0004,Utilities,Emergency Shutdown,2021-12-28,7,8,10.19,0.583,21209,0,0 TA-00001003,REF-0006,Hydrocracker,Planned Turnaround,2027-02-09,28,32,10.93,0.824,91180,0,0 TA-00001004,REF-0015,Tank Farm,Planned Turnaround,2020-11-18,27,32,17.58,0.437,92175,0,0 TA-00001005,REF-0009,Cooling Water,Regulatory Outage,2027-01-26,20,21,4.9,0.742,62686,1,0 TA-00001006,REF-0012,Utilities,Major Turnaround,2021-01-05,28,33,17.28,0.43,19533,1,0 TA-00001007,REF-0009,Utilities,Emergency Shutdown,2019-06-23,7,9,15.85,0.823,43816,0,0 TA-00001008,REF-0002,Hydrotreating,Planned Turnaround,2024-05-10,34,39,14.23,0.912,43321,0,0 TA-00001009,REF-0002,CDU,Pitstop,2022-03-03,8,10,24.54,0.488,22807,0,0 TA-00001010,REF-0011,Hydrogen Plant,Pitstop,2026-01-26,5,6,5.54,0.779,75035,0,0 TA-00001011,REF-0001,Alkylation,Emergency Shutdown,2022-10-12,6,7,9.79,0.444,124591,0,0 TA-00001012,REF-0003,Tank Farm,Pitstop,2021-03-30,7,9,15.9,0.916,34883,0,0 TA-00001013,REF-0004,Reformer,Pitstop,2028-03-21,15,17,11.44,0.559,73548,0,0 TA-00001014,REF-0001,Alkylation,Emergency Shutdown,2019-01-13,5,6,14.84,0.449,128770,0,0 TA-00001015,REF-0002,VDU,Planned Turnaround,2023-05-30,33,38,13.41,0.682,101556,0,1 TA-00001016,REF-0006,VDU,Emergency Shutdown,2019-10-02,7,7,0.0,0.545,97592,0,0 TA-00001017,REF-0001,Hydrocracker,Major Turnaround,2021-05-12,21,25,14.82,0.795,117178,0,0 TA-00001018,REF-0015,Sulfur Recovery,Planned Turnaround,2024-03-20,23,25,5.97,0.919,64010,0,0 TA-00001019,REF-0012,Hydrogen Plant,Planned Turnaround,2025-06-16,19,20,4.84,0.15,23124,1,0 TA-00001020,REF-0003,Alkylation,Planned Turnaround,2025-06-24,32,36,9.94,0.672,129429,0,0 TA-00001021,REF-0010,CDU,Planned Turnaround,2022-01-24,19,20,2.92,0.591,72235,0,0 TA-00001022,REF-0003,FCCU,Planned Turnaround,2028-10-04,25,29,13.33,0.923,110086,0,0 TA-00001023,REF-0010,Sulfur Recovery,Planned Turnaround,2022-09-10,29,30,0.98,0.98,18656,0,0 TA-00001024,REF-0008,Sulfur Recovery,Planned Turnaround,2027-01-31,16,18,7.95,0.704,13627,0,0 TA-00001025,REF-0006,Sulfur Recovery,Planned Turnaround,2027-08-27,28,31,10.24,0.59,38648,0,0 TA-00001026,REF-0009,Tank Farm,Planned Turnaround,2022-10-27,20,24,15.24,0.484,72350,0,0 TA-00001027,REF-0002,Alkylation,Planned Turnaround,2026-12-29,29,31,4.56,0.791,16737,0,1 TA-00001028,REF-0008,Reformer,Planned Turnaround,2022-08-12,25,28,10.25,0.878,80054,0,0 TA-00001029,REF-0004,Hydrotreating,Major Turnaround,2019-09-03,38,41,6.93,0.533,39899,0,0 TA-00001030,REF-0010,Hydrotreating,Pitstop,2021-05-30,11,13,11.95,0.892,15480,1,0 TA-00001031,REF-0015,Cooling Water,Regulatory Outage,2020-07-01,19,22,12.43,0.643,69211,1,0 TA-00001032,REF-0009,Utilities,Emergency Shutdown,2028-11-08,7,8,12.78,0.479,70494,0,0 TA-00001033,REF-0013,Sulfur Recovery,Major Turnaround,2027-07-28,30,35,13.47,0.569,36363,0,0 TA-00001034,REF-0009,Hydrocracker,Planned Turnaround,2025-02-12,26,31,18.26,0.475,36185,0,0 TA-00001035,REF-0005,Flare System,Planned Turnaround,2020-02-09,29,32,9.85,0.607,62019,0,0 TA-00001036,REF-0012,VDU,Pitstop,2028-12-15,8,10,15.68,0.349,87819,1,0 TA-00001037,REF-0011,Tank Farm,Major Turnaround,2019-10-09,27,32,15.05,0.606,36545,0,0 TA-00001038,REF-0001,CDU,Regulatory Outage,2023-11-26,17,18,1.42,0.614,165192,1,0 TA-00001039,REF-0005,Hydrotreating,Regulatory Outage,2019-08-05,17,19,9.09,0.753,25575,1,0 TA-00001040,REF-0001,Flare System,Major Turnaround,2025-06-13,39,45,14.13,0.725,111267,0,0 TA-00001041,REF-0003,FCCU,Planned Turnaround,2020-06-09,25,29,12.3,0.365,144157,0,0 TA-00001042,REF-0004,Hydrocracker,Major Turnaround,2022-03-12,36,39,6.11,0.843,34555,1,0 TA-00001043,REF-0002,CDU,Planned Turnaround,2024-11-22,25,27,6.31,0.281,121081,0,0 TA-00001044,REF-0001,CDU,Planned Turnaround,2020-02-13,36,40,8.42,0.598,131255,0,0 TA-00001045,REF-0002,Reformer,Planned Turnaround,2023-04-07,28,31,9.01,0.484,28256,0,0 TA-00001046,REF-0012,VDU,Major Turnaround,2026-05-09,43,50,16.12,0.425,52889,0,0 TA-00001047,REF-0015,Utilities,Planned Turnaround,2026-09-19,21,23,9.08,0.473,147021,0,0 TA-00001048,REF-0011,Reformer,Emergency Shutdown,2020-12-08,8,10,21.39,0.98,90844,0,0 TA-00001049,REF-0013,Sulfur Recovery,Planned Turnaround,2026-01-16,22,27,19.23,0.835,36074,0,0 TA-00001050,REF-0012,Tank Farm,Planned Turnaround,2021-08-26,18,21,12.02,0.692,46738,0,0 TA-00001051,REF-0012,Flare System,Pitstop,2026-10-05,10,12,10.25,0.704,47645,1,0 TA-00001052,REF-0013,Tank Farm,Major Turnaround,2024-11-23,44,49,9.59,0.431,63522,0,0 TA-00001053,REF-0002,Delayed Coker,Planned Turnaround,2019-10-27,23,26,9.3,0.562,74613,0,1 TA-00001054,REF-0004,Hydrotreating,Planned Turnaround,2027-09-16,22,26,16.94,0.597,14143,0,0 TA-00001055,REF-0004,FCCU,Planned Turnaround,2019-01-26,33,36,7.89,0.588,8120,0,1 TA-00001056,REF-0007,VDU,Regulatory Outage,2025-02-10,16,19,13.29,0.742,107471,1,0 TA-00001057,REF-0011,CDU,Planned Turnaround,2026-05-07,20,23,12.91,0.629,55707,1,1 TA-00001058,REF-0015,Alkylation,Regulatory Outage,2025-05-17,14,16,13.38,0.635,100832,1,0 TA-00001059,REF-0007,Hydrocracker,Planned Turnaround,2020-08-11,17,20,12.47,0.642,103291,0,0 TA-00001060,REF-0012,Tank Farm,Planned Turnaround,2022-07-03,28,33,16.45,0.477,146906,0,0 TA-00001061,REF-0010,Utilities,Major Turnaround,2028-02-13,40,45,11.47,0.439,51050,0,0 TA-00001062,REF-0003,Flare System,Planned Turnaround,2021-09-21,25,29,15.17,0.39,129734,0,1 TA-00001063,REF-0011,Hydrogen Plant,Planned Turnaround,2020-08-30,27,30,8.31,0.659,128064,0,0 TA-00001064,REF-0007,Alkylation,Planned Turnaround,2019-05-08,25,28,9.35,0.596,42715,0,0 TA-00001065,REF-0015,Tank Farm,Planned Turnaround,2020-10-17,25,28,8.85,0.416,139515,0,0 TA-00001066,REF-0004,Utilities,Planned Turnaround,2025-02-11,30,33,8.38,0.521,18614,0,1 TA-00001067,REF-0013,CDU,Planned Turnaround,2025-10-15,31,34,7.69,0.974,29954,1,0 TA-00001068,REF-0015,Hydrocracker,Major Turnaround,2026-02-16,19,23,18.39,0.78,153304,0,0 TA-00001069,REF-0010,Delayed Coker,Planned Turnaround,2028-09-13,26,30,11.86,0.7,74259,1,0 TA-00001070,REF-0009,Utilities,Regulatory Outage,2022-09-23,21,24,12.59,0.728,22320,1,0 TA-00001071,REF-0007,Flare System,Planned Turnaround,2020-09-21,32,37,12.55,0.867,94390,0,0 TA-00001072,REF-0010,Cooling Water,Planned Turnaround,2021-05-22,32,36,11.01,0.694,72277,0,0 TA-00001073,REF-0012,Tank Farm,Planned Turnaround,2021-02-10,27,31,11.72,0.524,123903,0,0 TA-00001074,REF-0008,Reformer,Planned Turnaround,2019-06-02,29,33,11.99,0.296,35072,0,0 TA-00001075,REF-0007,Alkylation,Planned Turnaround,2028-12-04,16,19,12.77,0.651,103614,0,0 TA-00001076,REF-0003,Delayed Coker,Planned Turnaround,2025-02-04,28,31,7.31,0.578,156618,0,0 TA-00001077,REF-0009,CDU,Planned Turnaround,2019-12-23,28,34,17.92,0.721,31072,0,0 TA-00001078,REF-0009,Hydrotreating,Pitstop,2025-04-02,7,8,8.26,0.559,51521,0,0 TA-00001079,REF-0010,Reformer,Planned Turnaround,2021-01-06,15,17,12.18,0.653,47319,0,0 TA-00001080,REF-0002,VDU,Planned Turnaround,2024-04-16,17,19,9.74,0.643,112299,1,0 TA-00001081,REF-0005,Hydrocracker,Pitstop,2023-08-29,14,16,8.43,0.315,51818,0,0 TA-00001082,REF-0005,CDU,Major Turnaround,2022-11-04,34,39,13.6,0.762,33705,1,0 TA-00001083,REF-0008,Cooling Water,Pitstop,2027-05-13,11,13,10.14,0.676,17417,1,0 TA-00001084,REF-0004,Utilities,Pitstop,2027-08-19,8,10,17.08,0.637,14118,0,0 TA-00001085,REF-0007,Sulfur Recovery,Major Turnaround,2025-03-30,44,50,11.88,0.709,81755,0,0 TA-00001086,REF-0008,Reformer,Planned Turnaround,2019-11-28,37,41,10.65,0.456,19954,0,0 TA-00001087,REF-0005,Sulfur Recovery,Planned Turnaround,2022-01-13,43,51,16.67,0.939,97597,1,0 TA-00001088,REF-0002,Alkylation,Planned Turnaround,2025-06-19,19,21,6.97,0.362,77117,0,0 TA-00001089,REF-0005,Reformer,Planned Turnaround,2025-04-04,29,33,10.57,0.701,102126,1,0 TA-00001090,REF-0014,Flare System,Major Turnaround,2019-10-01,42,45,5.38,0.655,7314,0,0 TA-00001091,REF-0009,FCCU,Planned Turnaround,2019-07-17,30,35,15.71,0.583,81375,0,0 TA-00001092,REF-0008,Sulfur Recovery,Regulatory Outage,2028-05-08,18,21,12.81,0.98,70787,1,0 TA-00001093,REF-0003,Hydrogen Plant,Pitstop,2028-03-20,8,10,13.44,0.76,82871,0,0 TA-00001094,REF-0003,Utilities,Planned Turnaround,2019-03-17,23,29,22.85,0.35,135079,0,0 TA-00001095,REF-0014,FCCU,Planned Turnaround,2019-07-01,34,38,11.2,0.471,7159,0,0 TA-00001096,REF-0011,Tank Farm,Major Turnaround,2023-08-09,26,29,8.84,0.844,13861,0,0 TA-00001097,REF-0015,VDU,Planned Turnaround,2020-06-20,27,29,6.41,0.684,123752,1,0 TA-00001098,REF-0010,Hydrogen Plant,Planned Turnaround,2023-03-24,25,28,10.99,0.697,85661,0,0 TA-00001099,REF-0014,Utilities,Planned Turnaround,2026-09-26,29,32,9.89,0.541,16722,1,0 TA-00001100,REF-0010,Alkylation,Planned Turnaround,2026-04-26,23,27,14.11,0.316,15349,0,0 TA-00001101,REF-0014,Reformer,Regulatory Outage,2023-08-07,13,14,3.43,0.842,42055,1,0 TA-00001102,REF-0008,FCCU,Planned Turnaround,2023-07-29,30,34,11.92,0.61,81469,0,1 TA-00001103,REF-0004,Flare System,Planned Turnaround,2020-03-01,21,25,17.34,0.711,42737,0,0 TA-00001104,REF-0010,Hydrotreating,Planned Turnaround,2021-02-18,36,40,8.63,0.329,63619,0,0 TA-00001105,REF-0008,Hydrotreating,Planned Turnaround,2025-09-28,36,39,7.95,0.575,54871,0,0 TA-00001106,REF-0014,Reformer,Emergency Shutdown,2022-06-27,8,9,6.28,0.767,52931,0,0 TA-00001107,REF-0014,Sulfur Recovery,Emergency Shutdown,2023-05-13,7,8,12.26,0.377,31540,0,0 TA-00001108,REF-0008,Hydrogen Plant,Planned Turnaround,2026-07-01,35,39,11.1,0.597,56376,0,1 TA-00001109,REF-0015,Cooling Water,Planned Turnaround,2022-04-19,20,23,13.25,0.93,166223,1,0 TA-00001110,REF-0004,VDU,Major Turnaround,2021-01-07,39,45,15.2,0.68,55236,0,0 TA-00001111,REF-0012,Delayed Coker,Planned Turnaround,2021-10-15,32,35,8.31,0.526,15646,0,0 TA-00001112,REF-0006,FCCU,Planned Turnaround,2023-06-21,13,15,10.65,0.664,9098,0,0 TA-00001113,REF-0015,Flare System,Planned Turnaround,2025-09-15,23,27,13.47,0.652,56291,0,0 TA-00001114,REF-0010,Delayed Coker,Planned Turnaround,2021-09-05,11,13,10.49,0.65,11208,1,0 TA-00001115,REF-0006,Delayed Coker,Planned Turnaround,2026-06-08,21,25,16.36,0.672,98600,0,1 TA-00001116,REF-0015,CDU,Planned Turnaround,2025-12-29,23,25,6.96,0.77,79684,0,0 TA-00001117,REF-0012,Utilities,Planned Turnaround,2020-02-21,23,26,9.93,0.98,82335,0,0 TA-00001118,REF-0005,FCCU,Planned Turnaround,2021-01-04,26,31,16.09,0.877,86303,0,0 TA-00001119,REF-0010,Delayed Coker,Planned Turnaround,2019-06-15,23,25,7.15,0.485,27756,1,1 TA-00001120,REF-0013,Tank Farm,Planned Turnaround,2025-09-12,24,28,13.17,0.277,33396,0,0 TA-00001121,REF-0014,Tank Farm,Planned Turnaround,2020-11-13,22,25,10.17,0.626,36230,1,0 TA-00001122,REF-0007,Sulfur Recovery,Planned Turnaround,2022-02-19,26,30,15.09,0.666,23358,0,0 TA-00001123,REF-0015,Reformer,Planned Turnaround,2022-01-21,27,37,34.77,0.582,52779,0,0 TA-00001124,REF-0011,FCCU,Pitstop,2024-07-30,10,11,8.06,0.871,118778,0,0 TA-00001125,REF-0003,VDU,Planned Turnaround,2023-10-31,18,28,51.2,0.689,39165,0,0 TA-00001126,REF-0011,Alkylation,Planned Turnaround,2024-08-05,25,27,6.42,0.779,114282,0,1 TA-00001127,REF-0010,Cooling Water,Pitstop,2026-09-16,5,6,13.65,0.503,88570,0,0 TA-00001128,REF-0001,Alkylation,Pitstop,2026-02-25,8,10,16.99,0.959,122028,0,1 TA-00001129,REF-0002,Reformer,Planned Turnaround,2025-11-02,19,26,33.57,0.48,14807,0,0 TA-00001130,REF-0015,Cooling Water,Planned Turnaround,2020-05-25,20,23,14.61,0.938,21573,0,0 TA-00001131,REF-0006,Hydrotreating,Planned Turnaround,2025-01-23,27,28,2.89,0.527,41800,0,0 TA-00001132,REF-0005,Tank Farm,Pitstop,2023-02-13,8,9,11.29,0.634,53312,0,0 TA-00001133,REF-0002,Cooling Water,Pitstop,2020-06-08,8,10,14.94,0.49,93013,0,0 TA-00001134,REF-0004,Hydrotreating,Planned Turnaround,2019-10-30,35,38,6.6,0.189,78400,0,0 TA-00001135,REF-0014,Cooling Water,Planned Turnaround,2022-04-05,25,27,4.99,0.896,24942,0,0 TA-00001136,REF-0007,Alkylation,Regulatory Outage,2019-12-30,12,15,18.03,0.657,42951,1,0 TA-00001137,REF-0012,Delayed Coker,Pitstop,2026-05-05,16,19,15.17,0.625,50920,0,0 TA-00001138,REF-0003,CDU,Planned Turnaround,2023-06-30,20,23,14.49,0.549,130053,0,0 TA-00001139,REF-0009,Hydrocracker,Major Turnaround,2022-04-17,40,45,11.23,0.795,59400,0,0 TA-00001140,REF-0001,VDU,Planned Turnaround,2026-09-15,24,28,13.26,0.571,49314,1,0 TA-00001141,REF-0009,CDU,Planned Turnaround,2028-01-12,14,19,31.75,0.836,16802,0,0 TA-00001142,REF-0014,Utilities,Pitstop,2025-01-13,11,13,13.76,0.98,36834,0,0 TA-00001143,REF-0005,Reformer,Planned Turnaround,2027-05-23,33,38,14.22,0.653,14484,0,0 TA-00001144,REF-0002,Utilities,Planned Turnaround,2023-09-21,19,22,15.05,0.414,104739,0,0 TA-00001145,REF-0003,Delayed Coker,Major Turnaround,2024-07-06,37,42,12.2,0.738,137049,1,0 TA-00001146,REF-0008,Flare System,Major Turnaround,2026-09-28,42,48,13.12,0.511,72220,0,0 TA-00001147,REF-0009,Hydrocracker,Emergency Shutdown,2019-09-17,6,8,16.92,0.475,35667,0,0 TA-00001148,REF-0014,Cooling Water,Emergency Shutdown,2027-12-23,7,8,12.17,0.72,33037,1,1 TA-00001149,REF-0001,Sulfur Recovery,Pitstop,2025-03-01,11,13,9.21,0.653,32122,0,0 TA-00001150,REF-0014,Reformer,Major Turnaround,2024-11-25,42,50,17.79,0.434,51538,0,0 TA-00001151,REF-0001,Sulfur Recovery,Planned Turnaround,2026-01-30,26,29,9.57,0.654,96526,0,0 TA-00001152,REF-0008,Sulfur Recovery,Pitstop,2020-09-02,11,14,18.21,0.422,69005,0,0 TA-00001153,REF-0001,VDU,Planned Turnaround,2020-02-10,25,27,7.38,0.669,92670,1,0 TA-00001154,REF-0003,Hydrogen Plant,Planned Turnaround,2023-04-01,18,19,2.96,0.47,101817,0,0 TA-00001155,REF-0011,Hydrotreating,Regulatory Outage,2024-12-11,23,26,10.77,0.726,45193,1,0 TA-00001156,REF-0005,VDU,Major Turnaround,2021-01-25,39,44,12.36,0.98,91248,0,0 TA-00001157,REF-0011,Delayed Coker,Planned Turnaround,2024-02-15,29,32,9.46,0.446,109433,0,0 TA-00001158,REF-0012,Delayed Coker,Emergency Shutdown,2027-12-24,4,5,14.0,0.964,83939,0,0 TA-00001159,REF-0003,Utilities,Planned Turnaround,2020-05-06,23,26,9.84,0.656,118385,0,0 TA-00001160,REF-0005,VDU,Planned Turnaround,2028-05-19,23,27,15.12,0.98,106208,0,1 TA-00001161,REF-0014,Alkylation,Planned Turnaround,2025-08-12,31,35,12.64,0.61,27768,0,0 TA-00001162,REF-0015,Hydrocracker,Planned Turnaround,2021-03-20,20,24,16.49,0.946,63294,1,0 TA-00001163,REF-0001,Hydrogen Plant,Planned Turnaround,2021-09-05,23,27,13.33,0.768,150663,0,0 TA-00001164,REF-0001,Delayed Coker,Regulatory Outage,2022-08-02,19,21,7.79,0.77,145047,1,0 TA-00001165,REF-0014,Reformer,Major Turnaround,2020-11-28,27,31,11.87,0.638,54410,0,0 TA-00001166,REF-0009,FCCU,Planned Turnaround,2027-09-21,18,19,4.55,0.487,76230,0,0 TA-00001167,REF-0012,Hydrogen Plant,Planned Turnaround,2027-10-22,32,37,13.82,0.508,71968,0,0 TA-00001168,REF-0011,Sulfur Recovery,Planned Turnaround,2020-10-03,26,39,47.39,0.269,35480,0,0 TA-00001169,REF-0010,Cooling Water,Pitstop,2020-02-19,10,12,14.83,0.342,50120,0,0 TA-00001170,REF-0008,Delayed Coker,Pitstop,2028-10-24,7,9,17.65,0.39,43392,0,0 TA-00001171,REF-0009,Hydrocracker,Planned Turnaround,2020-08-27,29,32,8.74,0.572,17984,0,1 TA-00001172,REF-0009,Sulfur Recovery,Planned Turnaround,2020-10-03,31,35,11.74,0.501,32204,0,0 TA-00001173,REF-0013,Tank Farm,Planned Turnaround,2020-08-23,35,40,13.65,0.507,14835,0,0 TA-00001174,REF-0013,Alkylation,Planned Turnaround,2024-03-21,20,21,2.76,0.557,84656,0,0 TA-00001175,REF-0012,Delayed Coker,Planned Turnaround,2023-10-05,17,20,12.74,0.884,43140,0,0 TA-00001176,REF-0013,Hydrocracker,Pitstop,2020-09-23,14,21,45.63,0.476,37155,0,0 TA-00001177,REF-0015,Hydrogen Plant,Planned Turnaround,2019-09-14,27,32,17.03,0.868,62091,0,0 TA-00001178,REF-0001,Delayed Coker,Planned Turnaround,2024-08-05,37,40,6.66,0.635,107736,0,0 TA-00001179,REF-0011,Sulfur Recovery,Planned Turnaround,2025-02-06,24,30,22.32,0.39,118658,0,0 TA-00001180,REF-0007,Sulfur Recovery,Planned Turnaround,2020-08-03,26,31,16.55,0.314,55013,0,0 TA-00001181,REF-0010,Delayed Coker,Planned Turnaround,2026-05-26,26,28,6.36,0.742,67271,0,0 TA-00001182,REF-0007,Delayed Coker,Planned Turnaround,2025-04-28,21,25,15.83,0.47,73785,0,0 TA-00001183,REF-0015,Tank Farm,Planned Turnaround,2021-01-16,23,29,24.03,0.819,18616,0,0 TA-00001184,REF-0005,VDU,Major Turnaround,2027-01-31,57,61,6.45,0.606,67791,0,0 TA-00001185,REF-0004,FCCU,Planned Turnaround,2019-05-08,26,28,5.25,0.637,58044,0,0 TA-00001186,REF-0009,Hydrotreating,Pitstop,2026-06-15,15,15,0.0,0.581,61352,0,0 TA-00001187,REF-0005,Reformer,Major Turnaround,2022-11-24,29,33,10.98,0.809,35099,0,0 TA-00001188,REF-0012,Sulfur Recovery,Planned Turnaround,2025-11-14,23,26,10.86,0.801,40692,0,0 TA-00001189,REF-0005,Flare System,Planned Turnaround,2028-08-30,33,36,7.46,0.462,74158,1,0 TA-00001190,REF-0007,Hydrocracker,Planned Turnaround,2028-02-16,23,27,13.79,0.607,116474,0,0 TA-00001191,REF-0015,Sulfur Recovery,Planned Turnaround,2021-03-01,33,38,14.11,0.487,28084,0,0 TA-00001192,REF-0004,Hydrogen Plant,Planned Turnaround,2019-02-14,34,40,16.28,0.73,9253,0,0 TA-00001193,REF-0013,VDU,Planned Turnaround,2021-09-03,33,37,9.68,0.417,56100,0,0 TA-00001194,REF-0005,Hydrogen Plant,Planned Turnaround,2028-10-22,27,30,8.65,0.633,47746,0,0 TA-00001195,REF-0014,Cooling Water,Pitstop,2024-05-07,7,11,52.74,0.649,29664,0,0 TA-00001196,REF-0010,Reformer,Planned Turnaround,2025-10-26,35,43,20.07,0.708,51249,0,0 TA-00001197,REF-0006,Alkylation,Pitstop,2028-03-08,8,9,10.55,0.624,18894,0,1 TA-00001198,REF-0004,Utilities,Major Turnaround,2027-10-07,36,40,9.95,0.885,21851,0,0 TA-00001199,REF-0005,Tank Farm,Planned Turnaround,2020-04-09,34,40,16.17,0.657,34408,1,0 TA-00001200,REF-0008,CDU,Planned Turnaround,2027-12-18,34,38,9.2,0.815,36797,0,0